22633 W WATERBURY ST 91364
Certificate Information: 22633 W WATERBURY ST 91364
- Application / Permit
- 24014-20000-03966
- Plan Check / Job No.
- B24VN15469
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION AT 1ST FLOOR TO CREATE A (N) BEDROOM AND AT 2ND FLOOR TO EXTEND BATHROOM WITH (N) BALCONY TO (E) 2-STORY S.F.D. PER ENGINEERING
- Permit Issued
- Issued on 3/7/2025
- Issuing Office
- Current Status
- CofO in Progress on 12/22/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/5/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/12/2024 | ALFRED RAMIREZ |
| Corrections Issued | 9/15/2024 | ALFRED RAMIREZ |
| Quality Review Completed | 9/19/2024 | STEVEN KIM |
| Applicant returned to address corrections | 10/24/2024 | ALFRED RAMIREZ |
| Applicant returned to address corrections | 11/7/2024 | ALFRED RAMIREZ |
| Applicant returned to address corrections | 1/28/2025 | ALFRED RAMIREZ |
| Plan Check Approved | 2/21/2025 | ALFRED RAMIREZ |
| Issued | 3/7/2025 | APPLICANT |
| CofO in Progress | 12/22/2025 | SEAN WIRCH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 10/30/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 10/31/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 10/31/2024 | BIAINA HARITUNIAN |
| Grading Pre-Inspection | Cleared | 11/5/2024 | CHARLES POWELL |
| ZA Case | Cleared | 11/6/2024 | NATHAN ROMINE |
| ZA Case | Cleared | 11/6/2024 | NATHAN ROMINE |
| Specific Plan | Cleared | 2/13/2025 | TIFFANY CORRALES |
| ZI | Cleared | 2/13/2025 | TIFFANY CORRALES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Shahbaz,, Shant Pierre; Lic. No.: C93079 | 15445 VENTURA BLVD #63 SHERMAN OAKS, CA 91403 |
Inspector Information
| JOHN HAYES, (818) 774-4302 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/28/2025 | Corrections Issued | JOHN COLEMAN |
| Deputy Drilled-In Anchors | 4/1/2025 | Conditional Approval | JOHN HAYES |
| Footing/Foundation/Slab | 4/2/2025 | Corrections Issued | JOHN HAYES |
| Footing/Foundation/Slab | 4/8/2025 | Approved | JOHN HAYES |
| Deputy Wood Construction | 5/15/2025 | Conditional Approval | JOHN HAYES |
| BUILDING-Rough-Frame | 5/16/2025 | Corrections Issued | JOHN HAYES |
| Green Building Rough | 5/16/2025 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 6/26/2025 | Corrections Issued | JOHN HAYES |
| ELECTRICAL-Rough | 6/26/2025 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 6/26/2025 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Rough | 6/26/2025 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 6/26/2025 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 7/11/2025 | Corrections Issued | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 7/11/2025 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 7/11/2025 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Rough | 7/11/2025 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 7/18/2025 | Partial Approval | JOHN HAYES |
| ELECTRICAL-Rough | 7/18/2025 | Not Ready for Inspection | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 7/18/2025 | Partial Approval | JOHN HAYES |
| Green Building Rough | 7/18/2025 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Rough | 7/18/2025 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 7/18/2025 | Not Ready for Inspection | JOHN HAYES |
| Interior/Exterior Lathing | 7/31/2025 | Partial Approval | JON MCHUGH |
| Shower Pan | 7/31/2025 | Approved | JON MCHUGH |
| BUILDING-Rough-Frame | 8/12/2025 | Not Ready for Inspection | SCOTT SOBEL |
| Green Building Rough | 8/12/2025 | Not Ready for Inspection | SCOTT SOBEL |
| Rough-Elec/Plmb/HVAC | 8/12/2025 | Partial Approval | SCOTT SOBEL |
| BUILDING-Rough-Frame | 8/21/2025 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Rough | 8/21/2025 | Approved | JOHN HAYES |
| Green Building Rough | 8/21/2025 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Rough | 8/21/2025 | Approved | JOHN HAYES |
| PLUMBING-Rough | 8/21/2025 | Approved | JOHN HAYES |
| BUILDING-Rough-Frame | 8/25/2025 | Approved | SCOTT SOBEL |
| Green Building Rough | 8/25/2025 | Approved | SCOTT SOBEL |
| Insulation | 8/29/2025 | Approved | SCOTT SOBEL |
| Drywall Nailing | 9/4/2025 | Approved | SCOTT SOBEL |
| Interior/Exterior Lathing | 9/4/2025 | Not Ready for Inspection | SCOTT SOBEL |
| Interior/Exterior Lathing | 9/26/2025 | Approved | SCOTT SOBEL |
| ELECTRICAL-Final | 12/22/2025 | Approved | SEAN WIRCH |
| Final | 12/22/2025 | OK to Issue CofO | SEAN WIRCH |
| Green Building Final | 12/22/2025 | Approved | SEAN WIRCH |
| HVAC-Final | 12/22/2025 | Approved | SEAN WIRCH |
| PLUMBING-Final | 12/22/2025 | Approved | SEAN WIRCH |
| SGSOV-Seismic Gas S/O Valve | 12/22/2025 | SGSOV Approved | SEAN WIRCH |
| Smoke Detectors | 12/22/2025 | Approved | SEAN WIRCH |