15658-15660 W LEMARSH ST 91343
Certificate Information: 15658-15660 W LEMARSH ST 91343
- Application / Permit
- 24014-20000-03954
- Plan Check / Job No.
- B24VN15413
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ATTACHED ADU ADDITION TO (E) 1 STORY SFD WITH ATTACHED GARAGE PER ENGINEER DESIGN (Attached ADU per Ordinance, LAMC 12.22 A.33(c) and (e) )
- Permit Issued
- Issued on 11/4/2024
- Issuing Office
- Current Status
- CofO Issued on 2/13/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/5/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/10/2024 | AUNG SOE |
| Corrections Issued | 9/12/2024 | AUNG SOE |
| Applicant returned to address corrections | 10/21/2024 | AUNG SOE |
| Applicant returned to address corrections | 10/30/2024 | CARLOS MONTES |
| Plan Check Approved | 11/1/2024 | CARLOS MONTES |
| Issued | 11/4/2024 | APPLICANT |
| CofO in Progress | 2/6/2025 | JENNIFER RABUCHIN |
| Permit Finaled | 2/13/2025 | RUBEN SALAS |
| CofO Issued | 2/13/2025 | RUBEN SALAS |
| Permit Finaled | 2/13/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 10/2/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 10/2/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 10/3/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 10/3/2024 | BIAINA HARITUNIAN |
| Certificate of Compliance | Cleared | 10/17/2024 | BRENNEN OBETO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Tavitian,, Rustom; Lic. No.: C92302 | 23705 VANOWEN ST #219 WEST HILLS, CA 91307 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/19/2024 | Approved | JAVIER RAMOS JR |
| Underground Mechanical | 11/22/2024 | Approved | KEVIN BERBERYAN |
| Excavation/Setback/Form/Re-Bar | 11/27/2024 | Approved | JAVIER RAMOS JR |
| Wood Frame | 12/18/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 12/23/2024 | Partial Approval | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 12/26/2024 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 12/26/2024 | Corrections Issued | JAVIER RAMOS JR |
| HVAC-Rough | 12/26/2024 | Corrections Issued | JAVIER RAMOS JR |
| Insulation | 12/26/2024 | Partial Inspection | JAVIER RAMOS JR |
| PLUMBING-Rough | 12/26/2024 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 12/30/2024 | Approved | LOUIS ESCOTO |
| HVAC-Rough | 12/30/2024 | Partial Inspection | LOUIS ESCOTO |
| Insulation | 12/30/2024 | Approved | LOUIS ESCOTO |
| Shower Pan | 12/30/2024 | Approved | LOUIS ESCOTO |
| Drywall Nailing | 1/2/2025 | Corrections Issued | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 1/2/2025 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 1/2/2025 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 1/27/2025 | Approved | MISAEL ESPARZA |
| Final | 1/27/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| Footing/Foundation/Slab | 1/27/2025 | Approved | MISAEL ESPARZA |
| Green Building Final | 1/27/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Rough | 1/27/2025 | Approved | MISAEL ESPARZA |
| MERV13>=Final | 1/27/2025 | Approved | MISAEL ESPARZA |
| MERV13>=Rough | 1/27/2025 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 1/27/2025 | SGSOV Approved | MISAEL ESPARZA |
| Smoke Detectors | 1/27/2025 | Approved | MISAEL ESPARZA |
| Drywall Nailing | 1/31/2025 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 1/31/2025 | Partial Inspection | JAVIER RAMOS JR |
| Final | 1/31/2025 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 1/31/2025 | Approved | JAVIER RAMOS JR |
| HVAC-Final | 1/31/2025 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 1/31/2025 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 1/31/2025 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 2/5/2025 | Approved | JENNIFER RABUCHIN |
| Final | 2/5/2025 | OK to Issue CofO | JENNIFER RABUCHIN |
| HVAC-Final | 2/5/2025 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 2/5/2025 | Approved | JENNIFER RABUCHIN |