8842 N AMBOY AVE 91352

Certificate Information: 8842 N AMBOY AVE 91352

Application / Permit
24014-20000-03951
Plan Check / Job No.
B24VN15406
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan: Detached 1-story garage conversion to ADU w/Addition per GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c),(d) and (g) . All work per WFPP
Permit Issued
Issued on 10/2/2024
Issuing Office
Current Status
CofO Issued on 9/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/5/2024 APPLICANT
Assigned to Plan Check Engineer 9/9/2024 DAVID CASTILLO
Corrections Issued 9/10/2024 DAVID CASTILLO
Plan Check Approved 9/30/2024 DAVID CASTILLO
Issued 10/2/2024 APPLICANT
CofO in Progress 9/5/2025 MATTHEW NELSON
CofO Issued 9/18/2025 RUBEN SALAS
Permit Finaled 9/18/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 9/24/2024 RYAN CASTRO
Roof/Waste drainage to street Cleared 9/24/2024 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 9/25/2024 RYAN CASTRO
Sewer availability Cleared 9/25/2024 RYAN CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

WILLIAM WREN, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/25/2024 Partial Approval DAVID MATSON
Sewer 11/25/2024 Approved DAVID MATSON
Underground Mechanical 11/25/2024 Partial Approval DAVID MATSON
Deputy Wood Construction 11/27/2024 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 11/27/2024 Corrections Issued MATTHEW NELSON
Footing/Foundation/Slab 12/4/2024 Corrections Issued MATTHEW NELSON
Excavation/Setback/Form/Re-Bar 12/9/2024 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 12/19/2024 Partial Approval MATTHEW NELSON
MERV13>=Rough 12/19/2024 Approved MATTHEW NELSON
BUILDING-Rough-Frame 12/31/2024 Partial Approval MATTHEW NELSON
ELECTRICAL-Rough 12/31/2024 Approved MATTHEW NELSON
HVAC-Rough 12/31/2024 Approved MATTHEW NELSON
PLUMBING-Rough 12/31/2024 Approved MATTHEW NELSON
Insulation 1/10/2025 Partial Approval MICHEL ABAJAN
Interior/Exterior Lathing 1/10/2025 Approved MICHEL ABAJAN
Shower Pan 1/10/2025 Approved MICHEL ABAJAN
Underground Mechanical 1/10/2025 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 1/21/2025 Approved MATTHEW NELSON
Insulation 1/21/2025 Approved MATTHEW NELSON
Drywall Nailing 2/7/2025 Approved MICHAEL CORTEZ
Interior/Exterior Lathing 2/7/2025 Approved MICHAEL CORTEZ
Final 3/7/2025 Corrections Issued MATTHEW NELSON
Footing/Foundation/Slab 3/7/2025 Approved MATTHEW NELSON
HVAC-Final 3/7/2025 Corrections Issued MATTHEW NELSON
MERV13>=Final 3/7/2025 Approved MATTHEW NELSON
PLUMBING-Final 3/7/2025 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 3/7/2025 SGSOV Approved MATTHEW NELSON
Smoke Detectors 3/7/2025 Approved MATTHEW NELSON
Final 9/4/2025 OK to Issue CofO MATTHEW NELSON