5756 E OMAHA ST 90042

Certificate Information: 5756 E OMAHA ST 90042

Application / Permit
24014-20000-03939
Plan Check / Job No.
B24VN15344
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION TO AND CONVERT DETACHED REC ROOM / STORAGE ROOM TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d).
Permit Issued
Issued on 1/29/2025
Issuing Office
Metro
Current Status
CofO Issued on 3/19/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/4/2024 APPLICANT
Assigned to Plan Check Engineer 9/7/2024 JEROME MAGAT PALMA
Corrections Issued 9/7/2024 JEROME MAGAT PALMA
Building Plans Picked Up 9/10/2024 APPLICANT
Plan Check Approved 11/15/2024 ISIS ARGUETA
Issued 1/29/2025 APPLICANT
CofO in Progress 3/19/2026 CHARLES BOGHOSKHAN
Permit Finaled 3/19/2026 DEROLD HAUFF
CofO Issued 3/19/2026 DEROLD HAUFF
Permit Finaled 3/19/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/13/2024 JEANIE LAM
Roof/Waste drainage to street Cleared 9/13/2024 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 9/17/2024 JEANIE LAM
Sewer availability Cleared 9/17/2024 JEANIE LAM
Grading Pre-Inspection Cleared 9/19/2024 GERMAN RODRIGUEZ MENDO

Contact Information

Contractor Williams Christopher; Lic. No.: 711380-B P O BOX 8652      LA CRESCENTA, CA 91224
Engineer Arakelyan,, Aram; Lic. No.: C82796 145 S GLENOAKS BI 328      BURBANK, CA 91502

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/7/2025 Partial Approval LILIANA PORTILLO
Deputy Drilled-In Anchors 3/18/2025 Conditional Approval LILIANA PORTILLO
Footing/Foundation/Slab 3/19/2025 Approved LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 4/10/2025 Partial Approval LILIANA PORTILLO
BUILDING-Rough-Frame 5/19/2025 Not Ready for Inspection LILIANA PORTILLO
ELECTRICAL-Rough 5/19/2025 Corrections Issued LILIANA PORTILLO
Green Building Rough 5/19/2025 Not Ready for Inspection LILIANA PORTILLO
HVAC-Rough 5/19/2025 Corrections Issued LILIANA PORTILLO
MERV13>=Rough 5/19/2025 Not Ready for Inspection LILIANA PORTILLO
PLUMBING-Rough 5/19/2025 Corrections Issued LILIANA PORTILLO
BUILDING-Rough-Frame 5/29/2025 Conditional Approval LILIANA PORTILLO
ELECTRICAL-Rough 5/29/2025 Approved LILIANA PORTILLO
Interior/Exterior Lathing 5/29/2025 Partial Approval LILIANA PORTILLO
PLUMBING-Rough 5/29/2025 Approved LILIANA PORTILLO
Underground Mechanical 5/29/2025 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 6/18/2025 Approved LILIANA PORTILLO
Green Building Rough 6/18/2025 Approved LILIANA PORTILLO
Insulation 6/18/2025 Approved LILIANA PORTILLO
MERV13>=Rough 6/18/2025 Approved LILIANA PORTILLO
Drywall Nailing 6/24/2025 Approved LILIANA PORTILLO
Interior/Exterior Lathing 7/15/2025 Approved BRENDAN MORELLI
Shower Pan 7/15/2025 Approved BRENDAN MORELLI
Final 1/8/2026 Not Ready for Inspection LILIANA PORTILLO
Green Building Final 1/8/2026 Not Ready for Inspection LILIANA PORTILLO
MERV13>=Final 1/8/2026 Not Ready for Inspection LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 1/8/2026 SGSOV Not Ready LILIANA PORTILLO
Smoke Detectors 1/8/2026 Not Ready for Inspection LILIANA PORTILLO
Service/Power Release 1/28/2026 Not Ready for Inspection DAVID WILLIAMS
Final 2/2/2026 Corrections Issued LILIANA PORTILLO
Green Building Final 2/2/2026 Not Ready for Inspection LILIANA PORTILLO
MERV13>=Final 2/2/2026 Not Ready for Inspection LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 2/2/2026 SGSOV No Gas LILIANA PORTILLO
Smoke Detectors 2/2/2026 Not Ready for Inspection LILIANA PORTILLO
Final 3/5/2026 Not Ready for Inspection LILIANA PORTILLO
Final 3/17/2026 OK to Issue CofO LILIANA PORTILLO
Green Building Final 3/17/2026 Approved LILIANA PORTILLO
MERV13>=Final 3/17/2026 Approved LILIANA PORTILLO
Service/Power Release 3/17/2026 Approved LILIANA PORTILLO
Smoke Detectors 3/17/2026 Approved LILIANA PORTILLO