20741-20743 W BERDON ST 91367
Certificate Information: 20741-20743 W BERDON ST 91367
- Application / Permit
- 24014-20000-03938
- Plan Check / Job No.
- B24VN15328
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL, 4'-0" X 27'-6" ADDITION TO (E) SFD ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 9/25/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/18/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/4/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/9/2024 | ARTIN ZARUKIAN |
| Corrections Issued | 9/9/2024 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 9/13/2024 | APPLICANT |
| Plan Check Approved | 9/25/2024 | SEWADA ZADOORAN MILAGARDI |
| Issued | 9/25/2024 | APPLICANT |
| CofO in Progress | 1/28/2025 | ALEXANDER HANDY |
| Permit Finaled | 3/18/2025 | JOHN JANSON |
| CofO Issued | 3/18/2025 | JOHN JANSON |
| Permit Finaled | 3/18/2025 | JOHN JANSON |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 9/13/2024 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 9/16/2024 | RYAN CASTRO |
| Grading Pre-Inspection | Cleared | 9/25/2024 | ARTIN ZARUKIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 60 VIA CARATAMA SAN CLEMENTE, CA 92673 |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/26/2024 | Partial Approval | ARUTYUN MADATYAN |
| Footing/Foundation/Slab | 9/30/2024 | Approved | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 10/18/2024 | Not Ready for Inspection | ALEXANDER HANDY |
| Floor/Roof Diaphrgm/Shear Wall | 10/18/2024 | Partial Approval | ALEXANDER HANDY |
| Green Building Rough | 10/18/2024 | Not Ready for Inspection | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 10/23/2024 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Rough | 10/23/2024 | Approved | ALEXANDER HANDY |
| Green Building Rough | 10/23/2024 | Approved | ALEXANDER HANDY |
| HVAC-Rough | 10/23/2024 | Approved | ALEXANDER HANDY |
| Interior/Exterior Lathing | 10/23/2024 | Partial Approval | ALEXANDER HANDY |
| PLUMBING-Rough | 10/23/2024 | Approved | ALEXANDER HANDY |
| Shower Pan | 10/23/2024 | Approved | ALEXANDER HANDY |
| Insulation | 10/25/2024 | Approved | ALEXANDER HANDY |
| Drywall Nailing | 10/30/2024 | Approved | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 10/30/2024 | Partial Inspection | ARUTYUN MADATYAN |
| Service/Power Release | 12/30/2024 | Approved | ALEXANDER HANDY |
| Final | 1/14/2025 | Corrections Issued | ALEXANDER HANDY |
| Green Building Final | 1/14/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 1/14/2025 | SGSOV Approved | ALEXANDER HANDY |
| Smoke Detectors | 1/14/2025 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Final | 1/27/2025 | Approved | ALEXANDER HANDY |
| Final | 1/27/2025 | OK to Issue CofO | ALEXANDER HANDY |
| Green Building Final | 1/27/2025 | Approved | ALEXANDER HANDY |
| HVAC-Final | 1/27/2025 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 1/27/2025 | Approved | ALEXANDER HANDY |
| Service/Power Release | 3/6/2025 | Approved | ALEXANDER HANDY |