18719 W VICTORY BLVD 91335

Certificate Information: 18719 W VICTORY BLVD 91335

Application / Permit
24014-20000-03900
Plan Check / Job No.
B24VN15103
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD 20'-2" X 20' & CONVERT (E) 17'-10" X 20' DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER LAMC 12.22A.33(c) & (d). WORK PER ENGINEER.
Permit Issued
Issued on 9/19/2024
Issuing Office
Valley
Current Status
CofO Issued on 10/16/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/30/2024 APPLICANT
Assigned to Plan Check Engineer 9/5/2024 HAYATO TSUCHIYA
Corrections Issued 9/5/2024 HAYATO TSUCHIYA
Building Plans Picked Up 9/6/2024 APPLICANT
Plan Check Approved 9/16/2024 ANGELICA MARTINEZ
Issued 9/19/2024 APPLICANT
CofO in Progress 10/9/2025 MORRIS JACKSON
Permit Finaled 10/16/2025 JOHN JANSON
CofO Issued 10/16/2025 JOHN JANSON
Permit Finaled 10/16/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 9/6/2024 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 9/6/2024 EDGAR ALCARAZ
Roof/Waste drainage to street Cleared 9/6/2024 EDGAR ALCARAZ
Sewer availability Cleared 9/6/2024 EDGAR ALCARAZ
ZI Cleared 9/10/2024 STEVEN WECHSLER

Contact Information

Contractor Owner-Builder       ,
Engineer Kia,, Babak; Lic. No.: C94091 21930 MARYLEE ST APT 87      WOODLAND HILLS, CA 91367

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/15/2024 Partial Inspection MORRIS JACKSON
Underground Mechanical 11/15/2024 Partial Approval MORRIS JACKSON
Deputy Drilled-In Anchors 1/17/2025 Conditional Approval MORRIS JACKSON
Footing/Foundation/Slab 1/17/2025 Approved MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 2/12/2025 Partial Approval MORRIS JACKSON
PLUMBING-Rough 2/12/2025 Not Ready for Inspection MORRIS JACKSON
ELECTRICAL-Rough 4/29/2025 Approved MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 4/29/2025 Partial Approval MORRIS JACKSON
Green Building Rough 4/29/2025 Approved MORRIS JACKSON
HVAC-Rough 4/29/2025 Approved MORRIS JACKSON
PLUMBING-Rough 4/29/2025 Approved MORRIS JACKSON
BUILDING-Rough-Frame 5/6/2025 Approved MORRIS JACKSON
Green Building Rough 5/6/2025 Approved MORRIS JACKSON
Interior/Exterior Lathing 5/6/2025 Partial Approval MORRIS JACKSON
Shower Pan 5/29/2025 Approved MORRIS JACKSON
Interior/Exterior Lathing 7/3/2025 Partial Approval MORRIS JACKSON
Insulation 8/1/2025 Approved MORRIS JACKSON
Drywall Nailing 8/8/2025 Approved JEFFREY HARTLINE
Final 9/22/2025 Corrections Issued MORRIS JACKSON
Green Building Final 9/22/2025 Approved MORRIS JACKSON
SGSOV-Seismic Gas S/O Valve 9/22/2025 SGSOV Not Ready MORRIS JACKSON
Smoke Detectors 9/22/2025 Approved MORRIS JACKSON
Final 9/26/2025 Corrections Issued JON MCHUGH
SGSOV-Seismic Gas S/O Valve 9/26/2025 SGSOV Approved JON MCHUGH
Final 9/30/2025 OK to Issue CofO MORRIS JACKSON