6855 N BOVEY AVE 91335
Certificate Information: 6855 N BOVEY AVE 91335
- Application / Permit
- 24014-20000-03896
- Plan Check / Job No.
- B24VN15092
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL, REMOVE REAR PATIO & 19'-6" X 31'-10" IRREGULAR SHAPED ADDITION TO (E) SINGLE FAMILY DWELLING.
- Permit Issued
- Issued on 9/11/2024
- Issuing Office
- Current Status
- CofO Issued on 3/28/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/30/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/5/2024 | ARTIN ZARUKIAN |
| Corrections Issued | 9/5/2024 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 9/6/2024 | APPLICANT |
| Plan Check Approved | 9/10/2024 | GIOVANNY CHAVEZ |
| Issued | 9/11/2024 | APPLICANT |
| CofO in Progress | 3/27/2025 | ARUTYUN MADATYAN |
| CofO Issued | 3/28/2025 | JOHN JANSON |
| Permit Finaled | 3/28/2025 | JOHN JANSON |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 9/6/2024 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 9/10/2024 | RYAN CASTRO |
| Sewer availability | Cleared | 9/10/2024 | RYAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Valencia,, Byron Steve; Lic. No.: C87372 | 16000 VENTURA BLVD., PH 1203 ENCINO, CA 91436 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 10/22/2024 | Approved | JEFFREY BULL |
| Special/Order Compliance | 10/22/2024 | Corrections Issued | JEFFREY BULL |
| Footing/Foundation/Slab | 10/25/2024 | Corrections Issued | JEFFREY BULL |
| Floor/Roof Diaphrgm/Shear Wall | 12/13/2024 | Corrections Issued | ARUTYUN MADATYAN |
| Deputy Wood Construction | 12/17/2024 | Conditional Approval | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/17/2024 | Partial Approval | ARUTYUN MADATYAN |
| PLUMBING-Rough | 12/17/2024 | Approved | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 1/28/2025 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Rough | 1/28/2025 | Approved | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/28/2025 | Approved | ARUTYUN MADATYAN |
| Green Building Rough | 1/28/2025 | Approved | ARUTYUN MADATYAN |
| HVAC-Rough | 1/28/2025 | Approved | ARUTYUN MADATYAN |
| Insulation | 1/31/2025 | Approved | ARUTYUN MADATYAN |
| Drywall Nailing | 2/6/2025 | Approved | JUAN ALVARADO |
| Interior/Exterior Lathing | 2/6/2025 | Approved | JUAN ALVARADO |
| Shower Pan | 2/6/2025 | Approved | JUAN ALVARADO |
| ELECTRICAL-Final | 3/14/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Final | 3/14/2025 | Corrections Issued | ARUTYUN MADATYAN |
| Footing/Foundation/Slab | 3/14/2025 | Approved | ARUTYUN MADATYAN |
| Green Building Final | 3/14/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| HVAC-Final | 3/14/2025 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Final | 3/14/2025 | Approved | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 3/14/2025 | SGSOV Approved | ARUTYUN MADATYAN |
| Smoke Detectors | 3/14/2025 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 3/26/2025 | Approved | ARUTYUN MADATYAN |
| Final | 3/26/2025 | OK to Issue CofO | ARUTYUN MADATYAN |
| Green Building Final | 3/26/2025 | Approved | ARUTYUN MADATYAN |
| HVAC-Final | 3/26/2025 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Final | 3/26/2025 | Approved | ARUTYUN MADATYAN |