17216 W DONMETZ ST 91344
Certificate Information: 17216 W DONMETZ ST 91344
- Application / Permit
- 24014-20000-03870
- Plan Check / Job No.
- B24VN14901
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION TO CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d).
- Permit Issued
- Issued on 9/18/2024
- Issuing Office
- Current Status
- CofO Issued on 2/20/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/29/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/5/2024 | JEROME MAGAT PALMA |
| Corrections Issued | 9/6/2024 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 9/9/2024 | APPLICANT |
| Plan Check Approved | 9/18/2024 | ROSENDO MEDINA |
| Issued | 9/18/2024 | APPLICANT |
| CofO in Progress | 2/7/2025 | STEVEN BACK |
| Permit Finaled | 2/20/2025 | JOHN JANSON |
| CofO Issued | 2/20/2025 | JOHN JANSON |
| Permit Finaled | 2/20/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 9/10/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 9/10/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 9/13/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 9/13/2024 | BIAINA HARITUNIAN |
| Construction near power lines | Cleared | 9/16/2024 | WALTER RAMIREZ |
| Grading Pre-Inspection | Cleared | 10/16/2024 | MICHAEL TEMPLE |
Contact Information
| Contractor | Real Remodeling Inc; Lic. No.: 1006772-B | 13351 RIVERSIDE DRIVE UNIT 201 SHERMAN OAKS, CA 91423 |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 60 VIA CARATAMA SAN CLEMENTE, CA 92673 |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/20/2024 | Approved | JEFFREY PARD |
| Footing/Foundation/Slab | 9/23/2024 | Corrections Issued | STEVEN BACK |
| PLUMBING-Rough | 9/23/2024 | Partial Approval | STEVEN BACK |
| Excavation/Setback/Form/Re-Bar | 9/26/2024 | Approved | DAVID SCANTLIN |
| Footing/Foundation/Slab | 9/26/2024 | Approved | DAVID SCANTLIN |
| Gas Test | 10/3/2024 | Partial Approval | STEVEN BACK |
| PLUMBING-Rough | 10/3/2024 | Not Ready for Inspection | STEVEN BACK |
| Sewer | 10/3/2024 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 10/7/2024 | Partial Approval | STEVEN BACK |
| BUILDING-Rough-Frame | 10/10/2024 | Corrections Issued | STEVEN BACK |
| ELECTRICAL-Rough | 10/10/2024 | Approved | STEVEN BACK |
| Green Building Rough | 10/10/2024 | Not Ready for Inspection | STEVEN BACK |
| Interior/Exterior Lathing | 10/10/2024 | Not Ready for Inspection | STEVEN BACK |
| PLUMBING-Rough | 10/10/2024 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 10/16/2024 | Corrections Issued | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 10/16/2024 | Approved | STEVEN BACK |
| Green Building Rough | 10/16/2024 | Corrections Issued | STEVEN BACK |
| BUILDING-Rough-Frame | 10/21/2024 | Corrections Issued | STEVEN BACK |
| Insulation | 10/21/2024 | Corrections Issued | STEVEN BACK |
| Special/Order Compliance | 10/21/2024 | Corrections Issued | STEVEN BACK |
| BUILDING-Rough-Frame | 10/28/2024 | Corrections Issued | STEVEN BACK |
| Green Building Rough | 10/28/2024 | Not Ready for Inspection | STEVEN BACK |
| HVAC-Rough | 10/28/2024 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 10/30/2024 | Approved | STEVEN BACK |
| Green Building Rough | 10/30/2024 | Approved | STEVEN BACK |
| Insulation | 10/30/2024 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 10/30/2024 | Partial Approval | STEVEN BACK |
| Drywall Nailing | 11/6/2024 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 11/12/2024 | Approved | STEVEN BACK |
| Shower Pan | 11/12/2024 | Approved | STEVEN BACK |
| Underground Mechanical | 11/19/2024 | Approved | STEVEN BACK |
| Final | 12/11/2024 | Corrections Issued | DAVID SCANTLIN |
| Green Building Final | 12/11/2024 | Not Ready for Inspection | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 12/11/2024 | SGSOV Approved | DAVID SCANTLIN |
| Smoke Detectors | 12/11/2024 | Approved | DAVID SCANTLIN |
| Final | 1/24/2025 | No Access for Inspection | STEVEN BACK |
| Green Building Final | 1/24/2025 | Approved | STEVEN BACK |
| Final | 2/7/2025 | OK to Issue CofO | STEVEN BACK |
| Service/Power Release | 2/7/2025 | Approved | STEVEN BACK |