17216 W DONMETZ ST 91344

Certificate Information: 17216 W DONMETZ ST 91344

Application / Permit
24014-20000-03870
Plan Check / Job No.
B24VN14901
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION TO CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d).
Permit Issued
Issued on 9/18/2024
Issuing Office
Current Status
CofO Issued on 2/20/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/29/2024 APPLICANT
Assigned to Plan Check Engineer 9/5/2024 JEROME MAGAT PALMA
Corrections Issued 9/6/2024 JEROME MAGAT PALMA
Building Plans Picked Up 9/9/2024 APPLICANT
Plan Check Approved 9/18/2024 ROSENDO MEDINA
Issued 9/18/2024 APPLICANT
CofO in Progress 2/7/2025 STEVEN BACK
Permit Finaled 2/20/2025 JOHN JANSON
CofO Issued 2/20/2025 JOHN JANSON
Permit Finaled 2/20/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 9/10/2024 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 9/10/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 9/13/2024 BIAINA HARITUNIAN
Sewer availability Cleared 9/13/2024 BIAINA HARITUNIAN
Construction near power lines Cleared 9/16/2024 WALTER RAMIREZ
Grading Pre-Inspection Cleared 10/16/2024 MICHAEL TEMPLE

Contact Information

Contractor Real Remodeling Inc; Lic. No.: 1006772-B 13351 RIVERSIDE DRIVE UNIT 201      SHERMAN OAKS, CA 91423
Engineer Standley,, Craig Erick; Lic. No.: C87675 60 VIA CARATAMA      SAN CLEMENTE, CA 92673

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/20/2024 Approved JEFFREY PARD
Footing/Foundation/Slab 9/23/2024 Corrections Issued STEVEN BACK
PLUMBING-Rough 9/23/2024 Partial Approval STEVEN BACK
Excavation/Setback/Form/Re-Bar 9/26/2024 Approved DAVID SCANTLIN
Footing/Foundation/Slab 9/26/2024 Approved DAVID SCANTLIN
Gas Test 10/3/2024 Partial Approval STEVEN BACK
PLUMBING-Rough 10/3/2024 Not Ready for Inspection STEVEN BACK
Sewer 10/3/2024 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 10/7/2024 Partial Approval STEVEN BACK
BUILDING-Rough-Frame 10/10/2024 Corrections Issued STEVEN BACK
ELECTRICAL-Rough 10/10/2024 Approved STEVEN BACK
Green Building Rough 10/10/2024 Not Ready for Inspection STEVEN BACK
Interior/Exterior Lathing 10/10/2024 Not Ready for Inspection STEVEN BACK
PLUMBING-Rough 10/10/2024 Approved STEVEN BACK
BUILDING-Rough-Frame 10/16/2024 Corrections Issued STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 10/16/2024 Approved STEVEN BACK
Green Building Rough 10/16/2024 Corrections Issued STEVEN BACK
BUILDING-Rough-Frame 10/21/2024 Corrections Issued STEVEN BACK
Insulation 10/21/2024 Corrections Issued STEVEN BACK
Special/Order Compliance 10/21/2024 Corrections Issued STEVEN BACK
BUILDING-Rough-Frame 10/28/2024 Corrections Issued STEVEN BACK
Green Building Rough 10/28/2024 Not Ready for Inspection STEVEN BACK
HVAC-Rough 10/28/2024 Approved STEVEN BACK
BUILDING-Rough-Frame 10/30/2024 Approved STEVEN BACK
Green Building Rough 10/30/2024 Approved STEVEN BACK
Insulation 10/30/2024 Approved STEVEN BACK
Interior/Exterior Lathing 10/30/2024 Partial Approval STEVEN BACK
Drywall Nailing 11/6/2024 Approved STEVEN BACK
Interior/Exterior Lathing 11/12/2024 Approved STEVEN BACK
Shower Pan 11/12/2024 Approved STEVEN BACK
Underground Mechanical 11/19/2024 Approved STEVEN BACK
Final 12/11/2024 Corrections Issued DAVID SCANTLIN
Green Building Final 12/11/2024 Not Ready for Inspection DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 12/11/2024 SGSOV Approved DAVID SCANTLIN
Smoke Detectors 12/11/2024 Approved DAVID SCANTLIN
Final 1/24/2025 No Access for Inspection STEVEN BACK
Green Building Final 1/24/2025 Approved STEVEN BACK
Final 2/7/2025 OK to Issue CofO STEVEN BACK
Service/Power Release 2/7/2025 Approved STEVEN BACK