5661 N ENSIGN AVE 91601

Certificate Information: 5661 N ENSIGN AVE 91601

Application / Permit
24014-20000-03851
Plan Check / Job No.
B24VN14747
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE INTO (N) ACCESSORY DWELLING UNIT PER LAMC (c)(d) & ADD 2-STORY **ePlan**
Permit Issued
Issued on 11/21/2024
Issuing Office
Current Status
CofO Issued on 1/28/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/29/2024 APPLICANT
Assigned to Plan Check Engineer 9/12/2024 NILOOFAR MEHRAIN
Corrections Issued 9/16/2024 NILOOFAR MEHRAIN
Quality Review Completed 9/16/2024 JASON HEALEY
Applicant returned to address corrections 10/4/2024 NILOOFAR MEHRAIN
Plan Check Approved 10/23/2024 NILOOFAR MEHRAIN
Issued 11/21/2024 APPLICANT
No Progress 1/14/2026 RAUL OLAGI
CofO in Progress 1/14/2026 RAUL OLAGI
CofO in Progress 1/14/2026 RAUL OLAGI
Permit Finaled 1/28/2026 RUBEN SALAS
Permit Finaled 1/28/2026 RUBEN SALAS
CofO Issued 1/28/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 9/18/2024 RYAN CASTRO
Roof/Waste drainage to street Cleared 9/18/2024 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 9/24/2024 RYAN CASTRO
Sewer availability Cleared 9/24/2024 RYAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Raab,, Andres Gustavo; Lic. No.: C52713 13645 SHABLOW AVE      SYLMAR, CA 91342

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/5/2025 Corrections Issued JOSE AVILA
Deputy Drilled-In Anchors 3/11/2025 Conditional Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 3/17/2025 Approved JOSE AVILA
Underground Mechanical 3/17/2025 Partial Approval JOSE AVILA
BUILDING-Rough-Frame 4/4/2025 Corrections Issued JOSE AVILA
Deputy Reinf. Concrete 4/15/2025 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 5/19/2025 Partial Approval JOSE AVILA
PLUMBING-Rough 6/20/2025 Corrections Issued JOSE AVILA
ELECTRICAL-Rough 7/8/2025 Partial Approval JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 7/8/2025 Approved JOSE AVILA
PLUMBING-Rough 7/8/2025 Approved JOSE AVILA
HVAC-Rough 7/22/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 7/22/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
Shower Pan 7/22/2025 Approved ROBERTO PALACIOS-LOPEZ
HVAC-Rough 7/30/2025 Not Ready for Inspection JOSE AVILA
BUILDING-Rough-Frame 8/8/2025 Approved JOSE AVILA
HVAC-Rough 8/8/2025 Approved JOSE AVILA
Insulation 8/18/2025 Approved JOSE AVILA
Drywall Nailing 8/25/2025 Approved JOSE AVILA
Interior/Exterior Lathing 9/10/2025 Approved LOUIS ESCOTO
Final 11/12/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 11/12/2025 Approved ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 11/12/2025 SGSOV Not Ready ROBERTO PALACIOS-LOPEZ
Smoke Detectors 11/12/2025 Approved ROBERTO PALACIOS-LOPEZ
Final 12/2/2025 Corrections Issued JOSE AVILA
SGSOV-Seismic Gas S/O Valve 12/2/2025 SGSOV No Gas JOSE AVILA
Final 12/12/2025 Corrections Issued JOSE AVILA
Final 1/14/2026 OK to Issue CofO JOSE AVILA