8942 N SNOWDEN AVE 91331

Certificate Information: 8942 N SNOWDEN AVE 91331

Application / Permit
24014-20000-03829
Plan Check / Job No.
B24VN14621
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: Convert (E) Detached Garage and new Addition for new Accessory Dwelling Unit per Ordinance LAMC 12.22 A.33(c)(d) .
Permit Issued
Issued on 12/30/2025
Issuing Office
Current Status
Issued on 12/30/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/28/2024 APPLICANT
Assigned to Plan Check Engineer 9/3/2024 KELVIN CHUONG
Corrections Issued 9/4/2024 KELVIN CHUONG
Applicant returned to address corrections 7/29/2025 GEORGE ALVAREZ
Applicant returned to address corrections 9/19/2025 KELVIN CHUONG
Applicant returned to address corrections 11/19/2025 KELVIN CHUONG
Applicant returned to address corrections 11/24/2025 KELVIN CHUONG
Applicant returned to address corrections 11/26/2025 KELVIN CHUONG
Applicant returned to address corrections 12/2/2025 GEORGE ALVAREZ
Applicant returned to address corrections 12/4/2025 SUNMIN LEE
Plan Check Approved 12/8/2025 SUNMIN LEE
Issued 12/30/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 6/13/2025 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 6/13/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 6/16/2025 BIAINA HARITUNIAN
Sewer availability Cleared 6/16/2025 BIAINA HARITUNIAN
Construction near power lines Cleared 8/4/2025 GEVORK KARAPETYAN
Trees in Parkway Cleared 9/15/2025 RICHARD SANCHEZ
Permit Cleared 11/3/2025 WALLIE JONG

Contact Information

Contractor Owner-Builder       ,
Engineer Zand,, Hossein; Lic. No.: C35721 5175 CHAPALA DR      RIVERSIDE, CA 92507
Engineer Zhong,, Raymond; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/24/2026 Approved VINCENT HANLEY
Sewer 2/24/2026 Approved VINCENT HANLEY
Underground Mechanical 2/24/2026 Partial Approval VINCENT HANLEY
Deputy Drilled-In Anchors 3/16/2026 Conditional Approval DAVID MATSON
Footing/Foundation/Slab 3/17/2026 Approved OGANES TARAKHCHYAN
Deputy Wood Construction 5/4/2026 Conditional Approval DAVID MATSON
ELECTRICAL-Rough 6/9/2026 Approved OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 6/9/2026 Approved OGANES TARAKHCHYAN
HVAC-Rough 6/9/2026 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 6/9/2026 Approved OGANES TARAKHCHYAN
Rough-Elec/Plmb/HVAC 6/9/2026 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 6/16/2026 Partial Approval NICHOLAS TROWBRIDGE
Wood Frame 6/16/2026 Corrections Issued NICHOLAS TROWBRIDGE