5417 N GENTRY AVE 91607
Certificate Information: 5417 N GENTRY AVE 91607
- Application / Permit
- 24014-20000-03828
- Plan Check / Job No.
- B24VN14615
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan. 2-story addition and conversion of detached garage to an ADU per LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 12/18/2024
- Issuing Office
- Current Status
- CofO Issued on 3/13/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/27/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/29/2024 | REZA HAGHIGHAT |
| Corrections Issued | 8/31/2024 | REZA HAGHIGHAT |
| Quality Review Completed | 9/5/2024 | CHIHARU SUZUKI |
| Plan Check Approved | 12/18/2024 | REZA HAGHIGHAT |
| Issued | 12/18/2024 | APPLICANT |
| CofO in Progress | 2/26/2026 | JAVIER RAMOS JR |
| Permit Finaled | 3/13/2026 | RUBEN SALAS |
| CofO Issued | 3/13/2026 | RUBEN SALAS |
| Permit Finaled | 3/13/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 9/6/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 9/6/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 9/9/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 9/9/2024 | BIAINA HARITUNIAN |
| ZA Case | Cleared | 9/10/2024 | DAVID URITA |
| Specific Plan | Cleared | 9/16/2024 | JOANNA MARROQUIN |
| Construction near power lines | Cleared | 12/10/2024 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 12/12/2024 | JERRY KAO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 22814 DOLOROSA ST WOODLAND HILLS, CA 91367 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/19/2025 | Corrections Issued | JUAN VALENZUELA |
| PLUMBING-Rough | 2/19/2025 | Partial Approval | JUAN VALENZUELA |
| Deputy Reinf. Concrete | 2/27/2025 | Conditional Approval | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 2/27/2025 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 4/9/2025 | Corrections Issued | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 4/9/2025 | Not Ready for Inspection | JAVIER RAMOS JR |
| PLUMBING-Rough | 4/9/2025 | Corrections Issued | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 4/17/2025 | Not Ready for Inspection | JAVIER RAMOS JR |
| Green Building Rough | 4/17/2025 | Not Ready for Inspection | JAVIER RAMOS JR |
| PLUMBING-Rough | 4/17/2025 | Partial Approval | JAVIER RAMOS JR |
| Wood Frame | 4/18/2025 | Not Ready for Inspection | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 4/22/2025 | Not Ready for Inspection | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 4/22/2025 | Not Ready for Inspection | JAVIER RAMOS JR |
| PLUMBING-Rough | 4/22/2025 | Corrections Issued | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 4/29/2025 | Corrections Issued | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 4/29/2025 | Corrections Issued | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 4/29/2025 | Partial Approval | JAVIER RAMOS JR |
| Shower Pan | 4/29/2025 | Approved | JAVIER RAMOS JR |
| Sewer | 5/2/2025 | Corrections Issued | JAVIER RAMOS JR |
| Insulation | 5/8/2025 | Not Ready for Inspection | JAVIER RAMOS JR |
| Pre-Inspection | 5/8/2025 | Partial Approval | JAVIER RAMOS JR |
| Verify Sprinkler Sign Off | 5/8/2025 | Approved | JAVIER RAMOS JR |
| Special/Order Compliance | 5/9/2025 | No Access for Inspection | JAVIER RAMOS JR |
| Pre-Inspection | 7/2/2025 | Partial Approval | JAVIER RAMOS JR |
| Special/Order Compliance | 7/8/2025 | Corrections Issued | JAVIER RAMOS JR |
| Pre-Inspection | 7/10/2025 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 7/14/2025 | Corrections Issued | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 7/14/2025 | Partial Inspection | JAVIER RAMOS JR |
| HVAC-Rough | 7/14/2025 | Corrections Issued | JAVIER RAMOS JR |
| PLUMBING-Rough | 7/14/2025 | Approved | JAVIER RAMOS JR |
| Wood Frame | 7/14/2025 | Partial Inspection | JAVIER RAMOS JR |
| Sewer | 12/19/2025 | Approved | JAVIER RAMOS JR |
| Underground Mechanical | 12/19/2025 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 2/3/2026 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 2/3/2026 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Final | 2/3/2026 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 2/3/2026 | Approved | JAVIER RAMOS JR |
| Final | 2/3/2026 | Corrections Issued | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 2/3/2026 | Approved | JAVIER RAMOS JR |
| Green Building Final | 2/3/2026 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 2/3/2026 | Approved | JAVIER RAMOS JR |
| HVAC-Final | 2/3/2026 | Corrections Issued | JAVIER RAMOS JR |
| HVAC-Rough | 2/3/2026 | Approved | JAVIER RAMOS JR |
| Insulation | 2/3/2026 | Approved | JAVIER RAMOS JR |
| Pre-Inspection | 2/3/2026 | Partial Approval | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 2/3/2026 | SGSOV Not Required | JAVIER RAMOS JR |
| Smoke Detectors | 2/3/2026 | Approved | JAVIER RAMOS JR |
| HVAC-Final | 2/11/2026 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 2/11/2026 | Approved | JAVIER RAMOS JR |
| Final | 2/26/2026 | OK to Issue CofO | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 2/26/2026 | Approved | JAVIER RAMOS JR |