5417 N GENTRY AVE 91607

Certificate Information: 5417 N GENTRY AVE 91607

Application / Permit
24014-20000-03828
Plan Check / Job No.
B24VN14615
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan. 2-story addition and conversion of detached garage to an ADU per LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 12/18/2024
Issuing Office
Current Status
CofO Issued on 3/13/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/27/2024 APPLICANT
Assigned to Plan Check Engineer 8/29/2024 REZA HAGHIGHAT
Corrections Issued 8/31/2024 REZA HAGHIGHAT
Quality Review Completed 9/5/2024 CHIHARU SUZUKI
Plan Check Approved 12/18/2024 REZA HAGHIGHAT
Issued 12/18/2024 APPLICANT
CofO in Progress 2/26/2026 JAVIER RAMOS JR
Permit Finaled 3/13/2026 RUBEN SALAS
CofO Issued 3/13/2026 RUBEN SALAS
Permit Finaled 3/13/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 9/6/2024 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 9/6/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 9/9/2024 BIAINA HARITUNIAN
Sewer availability Cleared 9/9/2024 BIAINA HARITUNIAN
ZA Case Cleared 9/10/2024 DAVID URITA
Specific Plan Cleared 9/16/2024 JOANNA MARROQUIN
Construction near power lines Cleared 12/10/2024 RIDWAN HARDY
Hydrant and Access approval Cleared 12/12/2024 JERRY KAO

Contact Information

Contractor Owner-Builder       ,
Engineer Sivushenka,, Mikita; Lic. No.: C87698 22814 DOLOROSA ST      WOODLAND HILLS, CA 91367

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/19/2025 Corrections Issued JUAN VALENZUELA
PLUMBING-Rough 2/19/2025 Partial Approval JUAN VALENZUELA
Deputy Reinf. Concrete 2/27/2025 Conditional Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 2/27/2025 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 4/9/2025 Corrections Issued JAVIER RAMOS JR
ELECTRICAL-Rough 4/9/2025 Not Ready for Inspection JAVIER RAMOS JR
PLUMBING-Rough 4/9/2025 Corrections Issued JAVIER RAMOS JR
BUILDING-Rough-Frame 4/17/2025 Not Ready for Inspection JAVIER RAMOS JR
Green Building Rough 4/17/2025 Not Ready for Inspection JAVIER RAMOS JR
PLUMBING-Rough 4/17/2025 Partial Approval JAVIER RAMOS JR
Wood Frame 4/18/2025 Not Ready for Inspection JAVIER RAMOS JR
BUILDING-Rough-Frame 4/22/2025 Not Ready for Inspection JAVIER RAMOS JR
ELECTRICAL-Rough 4/22/2025 Not Ready for Inspection JAVIER RAMOS JR
PLUMBING-Rough 4/22/2025 Corrections Issued JAVIER RAMOS JR
BUILDING-Rough-Frame 4/29/2025 Corrections Issued JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 4/29/2025 Corrections Issued JAVIER RAMOS JR
Interior/Exterior Lathing 4/29/2025 Partial Approval JAVIER RAMOS JR
Shower Pan 4/29/2025 Approved JAVIER RAMOS JR
Sewer 5/2/2025 Corrections Issued JAVIER RAMOS JR
Insulation 5/8/2025 Not Ready for Inspection JAVIER RAMOS JR
Pre-Inspection 5/8/2025 Partial Approval JAVIER RAMOS JR
Verify Sprinkler Sign Off 5/8/2025 Approved JAVIER RAMOS JR
Special/Order Compliance 5/9/2025 No Access for Inspection JAVIER RAMOS JR
Pre-Inspection 7/2/2025 Partial Approval JAVIER RAMOS JR
Special/Order Compliance 7/8/2025 Corrections Issued JAVIER RAMOS JR
Pre-Inspection 7/10/2025 Partial Approval JAVIER RAMOS JR
ELECTRICAL-Rough 7/14/2025 Corrections Issued JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 7/14/2025 Partial Inspection JAVIER RAMOS JR
HVAC-Rough 7/14/2025 Corrections Issued JAVIER RAMOS JR
PLUMBING-Rough 7/14/2025 Approved JAVIER RAMOS JR
Wood Frame 7/14/2025 Partial Inspection JAVIER RAMOS JR
Sewer 12/19/2025 Approved JAVIER RAMOS JR
Underground Mechanical 12/19/2025 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 2/3/2026 Approved JAVIER RAMOS JR
Drywall Nailing 2/3/2026 Approved JAVIER RAMOS JR
ELECTRICAL-Final 2/3/2026 Approved JAVIER RAMOS JR
ELECTRICAL-Rough 2/3/2026 Approved JAVIER RAMOS JR
Final 2/3/2026 Corrections Issued JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 2/3/2026 Approved JAVIER RAMOS JR
Green Building Final 2/3/2026 Approved JAVIER RAMOS JR
Green Building Rough 2/3/2026 Approved JAVIER RAMOS JR
HVAC-Final 2/3/2026 Corrections Issued JAVIER RAMOS JR
HVAC-Rough 2/3/2026 Approved JAVIER RAMOS JR
Insulation 2/3/2026 Approved JAVIER RAMOS JR
Pre-Inspection 2/3/2026 Partial Approval JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 2/3/2026 SGSOV Not Required JAVIER RAMOS JR
Smoke Detectors 2/3/2026 Approved JAVIER RAMOS JR
HVAC-Final 2/11/2026 Approved JAVIER RAMOS JR
PLUMBING-Final 2/11/2026 Approved JAVIER RAMOS JR
Final 2/26/2026 OK to Issue CofO JAVIER RAMOS JR
Footing/Foundation/Slab 2/26/2026 Approved JAVIER RAMOS JR