13550 W HARTLAND ST 91405
Certificate Information: 13550 W HARTLAND ST 91405
- Application / Permit
- 24014-20000-03790
- Plan Check / Job No.
- B24VN14368
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO SFD AND RELOCATED (E) ATTA. GARAGE.
- Permit Issued
- Issued on 1/5/2025
- Issuing Office
- Current Status
- CofO Issued on 4/30/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/26/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/28/2024 | SERGIO MUNIZ |
| Corrections Issued | 8/29/2024 | SERGIO MUNIZ |
| Plan Check Approved | 10/20/2024 | SERGIO MUNIZ |
| Issued | 1/5/2025 | APPLICANT |
| CofO in Progress | 4/8/2026 | RAUL OLAGI |
| CofO Issued | 4/30/2026 | RUBEN SALAS |
| Permit Finaled | 4/30/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Permit | Cleared | 9/7/2024 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 9/7/2024 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 9/7/2024 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 9/16/2024 | LEE GUILBEAUX |
| Sewer availability | Cleared | 9/16/2024 | LEE GUILBEAUX |
| Trees in Parkway | Cleared | 10/15/2024 | MIGUEL ORNELAS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Baluyut,, Agustin Pangilinan; Lic. No.: C66025 | 22828 S CYPRESS DR CARSON, CA 90745 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/10/2025 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 2/10/2025 | Corrections Issued | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 2/13/2025 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 2/21/2025 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/7/2025 | Approved | GAREN HAYRAPETYAN |
| Deputy Wood Construction | 3/20/2025 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/20/2025 | Corrections Issued | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 4/8/2025 | Approved | GAREN HAYRAPETYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/8/2025 | Approved | GAREN HAYRAPETYAN |
| HVAC-Rough | 4/8/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| PLUMBING-Rough | 4/8/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| HVAC-Rough | 4/10/2025 | Approved | GAREN HAYRAPETYAN |
| PLUMBING-Rough | 4/10/2025 | Approved | GAREN HAYRAPETYAN |
| Wood Frame | 4/10/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| BUILDING-Rough-Frame | 4/14/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Green Building Rough | 4/14/2025 | Approved | GAREN HAYRAPETYAN |
| Interior/Exterior Lathing | 4/14/2025 | Approved | GAREN HAYRAPETYAN |
| Insulation | 4/15/2025 | Partial Approval | OGANES TARAKHCHYAN |
| Drywall Nailing | 4/18/2025 | Approved | GAREN HAYRAPETYAN |
| Interior/Exterior Lathing | 4/22/2025 | Approved | GAREN HAYRAPETYAN |
| Shower Pan | 4/22/2025 | Approved | GAREN HAYRAPETYAN |
| BUILDING-Rough-Frame | 9/12/2025 | Approved | OGANES TARAKHCHYAN |
| Final | 9/12/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Green Building Final | 9/12/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 9/12/2025 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| Smoke Detectors | 9/12/2025 | Approved | OGANES TARAKHCHYAN |
| Final | 12/1/2025 | OK to Issue CofO | WAYNE REGESTER |
| Green Building Final | 12/1/2025 | Approved | WAYNE REGESTER |
| SGSOV-Seismic Gas S/O Valve | 12/1/2025 | SGSOV Approved | WAYNE REGESTER |