13550 W HARTLAND ST 91405

Certificate Information: 13550 W HARTLAND ST 91405

Application / Permit
24014-20000-03790
Plan Check / Job No.
B24VN14368
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION TO SFD AND RELOCATED (E) ATTA. GARAGE.
Permit Issued
Issued on 1/5/2025
Issuing Office
Current Status
CofO Issued on 4/30/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/26/2024 APPLICANT
Assigned to Plan Check Engineer 8/28/2024 SERGIO MUNIZ
Corrections Issued 8/29/2024 SERGIO MUNIZ
Plan Check Approved 10/20/2024 SERGIO MUNIZ
Issued 1/5/2025 APPLICANT
CofO in Progress 4/8/2026 RAUL OLAGI
CofO Issued 4/30/2026 RUBEN SALAS
Permit Finaled 4/30/2026 RUBEN SALAS

Permit Application Clearance Information

Permit Cleared 9/7/2024 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 9/7/2024 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 9/7/2024 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 9/16/2024 LEE GUILBEAUX
Sewer availability Cleared 9/16/2024 LEE GUILBEAUX
Trees in Parkway Cleared 10/15/2024 MIGUEL ORNELAS

Contact Information

Contractor Owner-Builder       ,
Engineer Baluyut,, Agustin Pangilinan; Lic. No.: C66025 22828 S CYPRESS DR      CARSON, CA 90745

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/10/2025 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 2/10/2025 Corrections Issued OGANES TARAKHCHYAN
Footing/Foundation/Slab 2/13/2025 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 2/21/2025 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 3/7/2025 Approved GAREN HAYRAPETYAN
Deputy Wood Construction 3/20/2025 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 3/20/2025 Corrections Issued OGANES TARAKHCHYAN
ELECTRICAL-Rough 4/8/2025 Approved GAREN HAYRAPETYAN
Floor/Roof Diaphrgm/Shear Wall 4/8/2025 Approved GAREN HAYRAPETYAN
HVAC-Rough 4/8/2025 Corrections Issued GAREN HAYRAPETYAN
PLUMBING-Rough 4/8/2025 Corrections Issued GAREN HAYRAPETYAN
HVAC-Rough 4/10/2025 Approved GAREN HAYRAPETYAN
PLUMBING-Rough 4/10/2025 Approved GAREN HAYRAPETYAN
Wood Frame 4/10/2025 Not Ready for Inspection GAREN HAYRAPETYAN
BUILDING-Rough-Frame 4/14/2025 Corrections Issued GAREN HAYRAPETYAN
Green Building Rough 4/14/2025 Approved GAREN HAYRAPETYAN
Interior/Exterior Lathing 4/14/2025 Approved GAREN HAYRAPETYAN
Insulation 4/15/2025 Partial Approval OGANES TARAKHCHYAN
Drywall Nailing 4/18/2025 Approved GAREN HAYRAPETYAN
Interior/Exterior Lathing 4/22/2025 Approved GAREN HAYRAPETYAN
Shower Pan 4/22/2025 Approved GAREN HAYRAPETYAN
BUILDING-Rough-Frame 9/12/2025 Approved OGANES TARAKHCHYAN
Final 9/12/2025 Not Ready for Inspection OGANES TARAKHCHYAN
Green Building Final 9/12/2025 Not Ready for Inspection OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 9/12/2025 SGSOV Not Ready OGANES TARAKHCHYAN
Smoke Detectors 9/12/2025 Approved OGANES TARAKHCHYAN
Final 12/1/2025 OK to Issue CofO WAYNE REGESTER
Green Building Final 12/1/2025 Approved WAYNE REGESTER
SGSOV-Seismic Gas S/O Valve 12/1/2025 SGSOV Approved WAYNE REGESTER