11481 W ERWIN ST 91606
Certificate Information: 11481 W ERWIN ST 91606
- Application / Permit
- 24014-20000-03789
- Plan Check / Job No.
- B24VN12986
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan Convert detached 2 car garage to one story ADU per LAMC 12.22 A.33 (c) and (d). To be fully sprinklered NFPA 13D
- Permit Issued
- Issued on 3/10/2025
- Issuing Office
- Current Status
- CofO in Progress on 5/20/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/16/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/22/2024 | MARCELA FRANQUEZ |
| Corrections Issued | 8/24/2024 | MARCELA FRANQUEZ |
| Quality Review Completed | 9/4/2024 | TU HUA |
| Applicant returned to address corrections | 12/11/2024 | MARCELA FRANQUEZ |
| Applicant returned to address corrections | 12/24/2024 | MARCELA FRANQUEZ |
| Plan Check Approved | 1/23/2025 | MARCELA FRANQUEZ |
| Issued | 3/10/2025 | APPLICANT |
| CofO in Progress | 5/20/2026 | GAREN HAYRAPETYAN |
Permit Application Clearance Information
| Address approval | Cleared | 9/4/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 9/4/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 9/5/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 9/5/2024 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Barakat,, Fouad Chafic; Lic. No.: C67449 | 11 CEDARWOOD DR POMONA, CA 91766 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/12/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Deputy Drilled-In Anchors | 8/19/2025 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 8/19/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Excavation/Setback/Form/Re-Bar | 8/22/2025 | Partial Approval | JOSE AVILA |
| ELECTRICAL-Rough | 10/30/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 10/30/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 10/30/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 10/30/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Verify Sprinkler Sign Off | 10/30/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 11/7/2025 | Partial Approval | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 11/12/2025 | Partial Approval | JOSE AVILA |
| Footing/Foundation/Slab | 11/12/2025 | Approved | JOSE AVILA |
| HVAC-Rough | 12/4/2025 | Approved | JOSE AVILA |
| Deputy Wood Construction | 12/5/2025 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 12/10/2025 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 12/16/2025 | Approved | JOSE AVILA |
| PLUMBING-Rough | 12/16/2025 | Approved | JOSE AVILA |
| Insulation | 12/22/2025 | Corrections Issued | JAVIER RAMOS JR |
| Verify Sprinkler Sign Off | 12/22/2025 | Approved | JAVIER RAMOS JR |
| Insulation | 12/29/2025 | Partial Inspection | JAVIER RAMOS JR |
| Shower Pan | 12/29/2025 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 1/8/2026 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 1/8/2026 | Approved | JOSE AVILA |
| Insulation | 1/12/2026 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 2/4/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| Drywall Nailing | 2/4/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 2/4/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| Sewer | 2/11/2026 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 4/23/2026 | Corrections Issued | GAREN HAYRAPETYAN |
| Green Building Final | 4/23/2026 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| SGSOV-Seismic Gas S/O Valve | 4/23/2026 | SGSOV Approved | GAREN HAYRAPETYAN |
| Smoke Detectors | 4/23/2026 | Approved | GAREN HAYRAPETYAN |
| Final | 5/19/2026 | OK to Issue CofO | GAREN HAYRAPETYAN |
| Green Building Final | 5/19/2026 | Approved | GAREN HAYRAPETYAN |