8600 N SYLMAR AVE 91402

Certificate Information: 8600 N SYLMAR AVE 91402

Application / Permit
24014-20000-03786
Plan Check / Job No.
B24VN14342
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) ADDITION TO (E) SFD
Permit Issued
Issued on 8/26/2025
Issuing Office
Current Status
CofO Issued on 1/23/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/23/2024 APPLICANT
Assigned to Plan Check Engineer 8/28/2024 DANIEL ABRAMYAN
Corrections Issued 8/28/2024 DANIEL ABRAMYAN
Applicant returned to address corrections 3/6/2025 ISIS ARGUETA
Applicant returned to address corrections 7/11/2025 ISIS ARGUETA
Plan Check Approved 8/2/2025 ISIS ARGUETA
Issued 8/26/2025 APPLICANT
CofO in Progress 1/6/2026 MICHEL ABAJAN
Permit Finaled 1/23/2026 RUBEN SALAS
Permit Finaled 1/23/2026 RUBEN SALAS
CofO Issued 1/23/2026 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 2/11/2025 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 3/4/2025 BIAINA HARITUNIAN
Sewer availability Cleared 3/4/2025 BIAINA HARITUNIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Fernandez,, Samuel; Lic. No.: C70886 8225 BRIMFIELD AVE      PANORAMA CITY, CA 91402

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/5/2025 Conditional Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 9/10/2025 Approved VINCENT HANLEY
Footing/Foundation/Slab 9/10/2025 Approved VINCENT HANLEY
BUILDING-Rough-Frame 9/16/2025 Partial Approval VINCENT HANLEY
PLUMBING-Rough 9/16/2025 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 9/17/2025 Partial Approval VINCENT HANLEY
Insulation 9/17/2025 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 10/8/2025 Approved VINCENT HANLEY
ELECTRICAL-Rough 10/8/2025 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 10/8/2025 Approved VINCENT HANLEY
Green Building Rough 10/8/2025 Approved VINCENT HANLEY
HVAC-Rough 10/8/2025 Approved VINCENT HANLEY
PLUMBING-Rough 10/8/2025 Approved VINCENT HANLEY
Insulation 10/10/2025 Corrections Issued MICHAEL CORTEZ
Interior/Exterior Lathing 10/10/2025 Not Ready for Inspection MICHAEL CORTEZ
Shower Pan 10/10/2025 Approved MICHAEL CORTEZ
Insulation 10/20/2025 Approved MICHEL ABAJAN
Interior/Exterior Lathing 10/20/2025 Approved MICHEL ABAJAN
Drywall Nailing 11/4/2025 Approved MISAEL ESPARZA
Interior/Exterior Lathing 11/4/2025 Approved MISAEL ESPARZA
ELECTRICAL-Final 1/5/2026 Approved MICHEL ABAJAN
Final 1/5/2026 OK to Issue CofO MICHEL ABAJAN
HVAC-Final 1/5/2026 Approved MICHEL ABAJAN
PLUMBING-Final 1/5/2026 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 1/5/2026 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 1/5/2026 Approved MICHEL ABAJAN