9925 N WEALTHA AVE 91352

Certificate Information: 9925 N WEALTHA AVE 91352

Application / Permit
24014-20000-03775
Plan Check / Job No.
B24VN14304
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW ADDITION TO AND REMODEL OF EXISTING SINGLE FAMILY DWELLING TO EXTEND LAUNDRY ROOM AND RENOVATE KITCHEN. WORK DONE PER ENGINEER DESIGN.
Permit Issued
Issued on 10/2/2024
Issuing Office
Valley
Current Status
CofO Issued on 2/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/23/2024 APPLICANT
Assigned to Plan Check Engineer 8/29/2024 JESSE ARELLANO
Corrections Issued 8/30/2024 JESSE ARELLANO
Building Plans Picked Up 9/3/2024 APPLICANT
Plan Check Approved 9/30/2024 HAYATO TSUCHIYA
Issued 10/2/2024 APPLICANT
CofO in Progress 2/5/2025 DAVID ANDERSON
Permit Finaled 2/18/2025 RUBEN SALAS
CofO Issued 2/18/2025 RUBEN SALAS
Permit Finaled 2/18/2025 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/23/2024 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 9/23/2024 BIAINA HARITUNIAN
Specific Plan Cleared 9/26/2024 JOSHUA ORDONEZ
Grading Pre-Inspection Cleared 9/27/2024 CHARLES POWELL

Contact Information

Contractor A Sunrise Roofing Inc; Lic. No.: 890777-B 19503 STRATHERN ST      RESEDA, CA 91335
Engineer Garcia,, Francisco Diaz; Lic. No.: C88029 19145 MALABAR ST      SANTA CLARITA, CA 91351

Inspector Information

DAVID ANDERSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/5/2024 Approved DAVID ANDERSON
METHANE-Barrier 11/5/2024 Approved DAVID ANDERSON
METHANE-Final 11/5/2024 Approved DAVID ANDERSON
METHANE-Rough 11/5/2024 Approved DAVID ANDERSON
METHANE-Subgrade 11/5/2024 Approved DAVID ANDERSON
BUILDING-Rough-Frame 11/27/2024 Approved DAVID ANDERSON
ELECTRICAL-Rough 11/27/2024 Approved DAVID ANDERSON
Green Building Rough 11/27/2024 Approved DAVID ANDERSON
PLUMBING-Rough 11/27/2024 Approved DAVID ANDERSON
Drywall Nailing 12/4/2024 Approved DAVID ANDERSON
Insulation 12/4/2024 Approved DAVID ANDERSON
ELECTRICAL-Final 1/29/2025 Not Ready for Inspection KEVIN BERBERYAN
Final 1/29/2025 Corrections Issued KEVIN BERBERYAN
Green Building Final 1/29/2025 Approved KEVIN BERBERYAN
PLUMBING-Final 1/29/2025 Approved KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 1/29/2025 SGSOV Approved KEVIN BERBERYAN
Smoke Detectors 1/29/2025 Approved KEVIN BERBERYAN
Final 2/4/2025 OK to Issue CofO DAVID ANDERSON