9925 N WEALTHA AVE 91352
Certificate Information: 9925 N WEALTHA AVE 91352
- Application / Permit
- 24014-20000-03775
- Plan Check / Job No.
- B24VN14304
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW ADDITION TO AND REMODEL OF EXISTING SINGLE FAMILY DWELLING TO EXTEND LAUNDRY ROOM AND RENOVATE KITCHEN. WORK DONE PER ENGINEER DESIGN.
- Permit Issued
- Issued on 10/2/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/18/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/23/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/29/2024 | JESSE ARELLANO |
| Corrections Issued | 8/30/2024 | JESSE ARELLANO |
| Building Plans Picked Up | 9/3/2024 | APPLICANT |
| Plan Check Approved | 9/30/2024 | HAYATO TSUCHIYA |
| Issued | 10/2/2024 | APPLICANT |
| CofO in Progress | 2/5/2025 | DAVID ANDERSON |
| Permit Finaled | 2/18/2025 | RUBEN SALAS |
| CofO Issued | 2/18/2025 | RUBEN SALAS |
| Permit Finaled | 2/18/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/23/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 9/23/2024 | BIAINA HARITUNIAN |
| Specific Plan | Cleared | 9/26/2024 | JOSHUA ORDONEZ |
| Grading Pre-Inspection | Cleared | 9/27/2024 | CHARLES POWELL |
Contact Information
| Contractor | A Sunrise Roofing Inc; Lic. No.: 890777-B | 19503 STRATHERN ST RESEDA, CA 91335 |
| Engineer | Garcia,, Francisco Diaz; Lic. No.: C88029 | 19145 MALABAR ST SANTA CLARITA, CA 91351 |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/5/2024 | Approved | DAVID ANDERSON |
| METHANE-Barrier | 11/5/2024 | Approved | DAVID ANDERSON |
| METHANE-Final | 11/5/2024 | Approved | DAVID ANDERSON |
| METHANE-Rough | 11/5/2024 | Approved | DAVID ANDERSON |
| METHANE-Subgrade | 11/5/2024 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 11/27/2024 | Approved | DAVID ANDERSON |
| ELECTRICAL-Rough | 11/27/2024 | Approved | DAVID ANDERSON |
| Green Building Rough | 11/27/2024 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 11/27/2024 | Approved | DAVID ANDERSON |
| Drywall Nailing | 12/4/2024 | Approved | DAVID ANDERSON |
| Insulation | 12/4/2024 | Approved | DAVID ANDERSON |
| ELECTRICAL-Final | 1/29/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| Final | 1/29/2025 | Corrections Issued | KEVIN BERBERYAN |
| Green Building Final | 1/29/2025 | Approved | KEVIN BERBERYAN |
| PLUMBING-Final | 1/29/2025 | Approved | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 1/29/2025 | SGSOV Approved | KEVIN BERBERYAN |
| Smoke Detectors | 1/29/2025 | Approved | KEVIN BERBERYAN |
| Final | 2/4/2025 | OK to Issue CofO | DAVID ANDERSON |