5758 N CARTWRIGHT AVE 91601

Certificate Information: 5758 N CARTWRIGHT AVE 91601

Application / Permit
24014-20000-03764
Plan Check / Job No.
B24VN14228
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
***Eplan*** Addition to (E) single family dwelling w/ attached garage, scope of work to include: Enclose existing front porch, addition at front and new covered front porch
Permit Issued
Issued on 10/9/2024
Issuing Office
Current Status
CofO Issued on 5/6/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/25/2024 APPLICANT
Assigned to Plan Check Engineer 8/28/2024 EDWIN ESPIN
Corrections Issued 8/28/2024 EDWIN ESPIN
Plan Check Approved 9/30/2024 EDWIN ESPIN
Issued 10/9/2024 APPLICANT
CofO in Progress 5/2/2025 RYAN SALAZAR
Permit Finaled 5/6/2025 RUBEN SALAS
CofO Issued 5/6/2025 RUBEN SALAS
Permit Finaled 5/6/2025 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 9/4/2024 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 9/5/2024 RYAN CASTRO
Sewer availability Cleared 9/5/2024 RYAN CASTRO

Contact Information

Contractor Better Together Builders Inc; Lic. No.: 1047689-B       ,
Engineer Melchor,, Oscar Elias; Lic. No.: NA76828       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/19/2024 Partial Inspection JOSE AVILA
Footing/Foundation/Slab 12/9/2024 Corrections Issued JOSE AVILA
Footing/Foundation/Slab 12/10/2024 Partial Approval JOSE AVILA
Deputy Drilled-In Anchors 12/16/2024 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 12/16/2024 Partial Approval JOSE AVILA
Footing/Foundation/Slab 12/16/2024 Approved JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 12/19/2024 Corrections Issued JOSE AVILA
Deputy Wood Construction 12/20/2024 Conditional Approval JUAN VALENZUELA
ELECTRICAL-Rough 1/15/2025 Approved JOSE AVILA
PLUMBING-Rough 1/15/2025 Approved JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 1/23/2025 Approved ROBERTO PALACIOS-LOPEZ
Shower Pan 1/23/2025 Approved ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 1/30/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Rough 1/30/2025 Approved ROBERTO PALACIOS-LOPEZ
HVAC-Rough 1/30/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 1/30/2025 Approved ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 2/6/2025 Approved ROBERTO PALACIOS-LOPEZ
HVAC-Rough 2/6/2025 Approved ROBERTO PALACIOS-LOPEZ
Insulation 2/11/2025 Approved ROBERTO PALACIOS-LOPEZ
Drywall Nailing 2/18/2025 Approved ROBERTO PALACIOS-LOPEZ
Final 4/28/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Final 4/28/2025 Approved ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 4/28/2025 SGSOV Approved ROBERTO PALACIOS-LOPEZ
Smoke Detectors 4/28/2025 Approved ROBERTO PALACIOS-LOPEZ
Final 5/1/2025 OK to Issue CofO RYAN SALAZAR