7117 N NATICK AVE 91405

Certificate Information: 7117 N NATICK AVE 91405

Application / Permit
24014-20000-03743
Plan Check / Job No.
B24VN14138
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN-CONVERT (E) ATTACHED GARAGE AND (N) ADDITION 5' X 10'-5" TO BECOME PART OF SFD TO ADD A NEW BEDROOM AND BATHROOM. WORK DONE PER ENGINEER DESIGN.
Permit Issued
Issued on 1/2/2025
Issuing Office
Current Status
CofO Issued on 6/5/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/22/2024 APPLICANT
Assigned to Plan Check Engineer 8/27/2024 MADISON ODELL
Corrections Issued 8/28/2024 MADISON ODELL
Applicant returned to address corrections 9/18/2024 MADISON ODELL
Applicant returned to address corrections 10/12/2024 MADISON ODELL
Applicant returned to address corrections 10/29/2024 MADISON ODELL
Plan Check Approved 12/5/2024 ARAMIK SHAHMIRZAIAN
Issued 1/2/2025 APPLICANT
CofO in Progress 6/3/2025 RYAN SALAZAR
Permit Finaled 6/5/2025 RUBEN SALAS
CofO Issued 6/5/2025 RUBEN SALAS
Permit Finaled 6/5/2025 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/17/2024 CARLOS RAMIREZ
Roof/Waste drainage to street Cleared 9/17/2024 CARLOS RAMIREZ
Sewer availability Cleared 9/17/2024 CARLOS RAMIREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Grandhi,, Venkata Rohit; Lic. No.: C88709 7823 BOXWOOD CT      HIGHLAND, CA 92346

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/9/2025 Conditional Approval RAUL OLAGI
Footing/Foundation/Slab 1/13/2025 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 1/23/2025 Partial Approval RYAN SALAZAR
Green Building Rough 1/23/2025 Not Ready for Inspection RYAN SALAZAR
HVAC-Rough 1/23/2025 Not Ready for Inspection RYAN SALAZAR
PLUMBING-Rough 1/23/2025 Partial Approval RYAN SALAZAR
ELECTRICAL-Rough 1/31/2025 Not Ready for Inspection RYAN SALAZAR
HVAC-Rough 1/31/2025 Not Ready for Inspection RYAN SALAZAR
PLUMBING-Rough 1/31/2025 Approved RYAN SALAZAR
Wood Frame 1/31/2025 Corrections Issued RYAN SALAZAR
ELECTRICAL-Rough 2/13/2025 Approved GAREN HAYRAPETYAN
HVAC-Rough 2/13/2025 Corrections Issued GAREN HAYRAPETYAN
Wood Frame 2/13/2025 Corrections Issued GAREN HAYRAPETYAN
BUILDING-Rough-Frame 2/18/2025 Approved RYAN SALAZAR
Green Building Rough 2/18/2025 Approved RYAN SALAZAR
Insulation 2/24/2025 Approved LOUIS ESCOTO
Interior/Exterior Lathing 2/24/2025 Approved LOUIS ESCOTO
Drywall Nailing 3/5/2025 Approved RYAN SALAZAR
Final 5/12/2025 Corrections Issued RYAN SALAZAR
Green Building Final 5/12/2025 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 5/12/2025 SGSOV Approved RYAN SALAZAR
Smoke Detectors 5/12/2025 Approved RYAN SALAZAR
Final 5/21/2025 Partial Approval RYAN SALAZAR
Final 6/4/2025 OK to Issue CofO RYAN SALAZAR