16451-16453 W LOS ALIMOS ST 91344
Certificate Information: 16451-16453 W LOS ALIMOS ST 91344
- Application / Permit
- 24014-20000-03731
- Plan Check / Job No.
- B24VN14040
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: CONVERT (E) ATTACHED GARAGE WITH ADDITIONS INTO A (N) ATTACHED 2-STORY 19'-7" x 26'- 11" ACCESSORY DWELLING UNIT TO COMPLY WITH LAMC 12.22 A.33(c) and (e) PER ENGINEERING
- Permit Issued
- Issued on 12/12/2024
- Issuing Office
- Current Status
- CofO Issued on 8/14/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/27/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/12/2024 | ALFRED RAMIREZ |
| Corrections Issued | 9/17/2024 | ALFRED RAMIREZ |
| Quality Review Completed | 9/20/2024 | STEVEN KIM |
| Applicant returned to address corrections | 12/3/2024 | ALFRED RAMIREZ |
| Plan Check Approved | 12/11/2024 | ALFRED RAMIREZ |
| No Progress | 12/11/2024 | ALFRED RAMIREZ |
| Plan Check Approved | 12/11/2024 | ALFRED RAMIREZ |
| No Progress | 12/11/2024 | ALFRED RAMIREZ |
| Plan Check Approved | 12/11/2024 | ALFRED RAMIREZ |
| Issued | 12/12/2024 | APPLICANT |
| CofO in Progress | 8/14/2025 | CHRISTOPHER ROJAS |
| CofO in Progress | 8/14/2025 | CHRISTOPHER ROJAS |
| Permit Finaled | 8/14/2025 | RUBEN SALAS |
| CofO Issued | 8/14/2025 | RUBEN SALAS |
| Permit Finaled | 8/14/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 11/22/2024 | KEVIN CHUNG |
| Roof/Waste drainage to street | Cleared | 11/22/2024 | KEVIN CHUNG |
| Eng Process Fee Ord 176,300 | Cleared | 11/25/2024 | KEVIN CHUNG |
| Sewer availability | Cleared | 11/25/2024 | KEVIN CHUNG |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/10/2025 | Partial Approval | JAVIER RAMOS JR |
| Deputy Drilled-In Anchors | 1/13/2025 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 1/15/2025 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 1/23/2025 | Partial Approval | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 1/31/2025 | Partial Inspection | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 1/31/2025 | Corrections Issued | JAVIER RAMOS JR |
| Pre-Inspection | 2/6/2025 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 2/24/2025 | Corrections Issued | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 2/24/2025 | Not Ready for Inspection | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 2/24/2025 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Rough | 2/24/2025 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 2/24/2025 | No Access for Inspection | JAVIER RAMOS JR |
| PLUMBING-Rough | 2/24/2025 | Not Ready for Inspection | JAVIER RAMOS JR |
| HVAC-Rough | 3/4/2025 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 3/4/2025 | Partial Approval | JAVIER RAMOS JR |
| PLUMBING-Rough | 3/4/2025 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 3/13/2025 | Approved | JAVIER RAMOS JR |
| Shower Pan | 3/13/2025 | Approved | JAVIER RAMOS JR |
| Insulation | 3/19/2025 | Corrections Issued | LOUIS ESCOTO |
| Underground Mechanical | 3/24/2025 | Approved | CHRISTOPHER ROJAS |
| Drywall Nailing | 4/2/2025 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 4/21/2025 | Approved | NICHOLAS TROWBRIDGE |
| Shower Pan | 4/21/2025 | Approved | NICHOLAS TROWBRIDGE |
| BUILDING-Rough-Frame | 6/23/2025 | Approved | CHRISTOPHER ROJAS |
| Final | 6/23/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Gas Test | 6/23/2025 | Approved | CHRISTOPHER ROJAS |
| Green Building Final | 6/23/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 6/23/2025 | SGSOV Not Ready | CHRISTOPHER ROJAS |
| Smoke Detectors | 6/23/2025 | Approved | CHRISTOPHER ROJAS |
| Final | 7/9/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Green Building Final | 7/9/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 7/9/2025 | SGSOV Approved | CHRISTOPHER ROJAS |
| Final | 8/6/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Final | 8/6/2025 | Approved | CHRISTOPHER ROJAS |
| Final | 8/13/2025 | OK to Issue CofO | CHRISTOPHER ROJAS |
| Final | 8/14/2025 | OK to Issue CofO | CHRISTOPHER ROJAS |
| Service/Power Release | 8/14/2025 | Approved | CHRISTOPHER ROJAS |