10773 N LAS LUNITAS AVE 91042
Certificate Information: 10773 N LAS LUNITAS AVE 91042
- Application / Permit
- 24014-20000-03687
- Plan Check / Job No.
- B24VN13738
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN PROPOSED REMODEL AND GROUND/SECOND FLOOR ADDITION TO EXPAND EXISTING SFD, ADDITION WILL INCLUDE 1-CAR GARAGE AND SECOND FLOOR COVERED DECK. ***SHALL BE SPRINKLERED PER NFPA 13D***
- Permit Issued
- Issued on 1/28/2025
- Issuing Office
- Current Status
- Issued on 1/28/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/24/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/5/2024 | MICHAEL LOPEZ |
| Corrections Issued | 9/14/2024 | MICHAEL LOPEZ |
| Quality Review Completed | 9/17/2024 | PRANITA SHAH |
| Applicant returned to address corrections | 12/31/2024 | MICHAEL LOPEZ |
| Plan Check Approved | 1/8/2025 | MICHAEL LOPEZ |
| Plan Check Approved | 1/27/2025 | MICHAEL LOPEZ |
| Issued | 1/28/2025 | APPLICANT |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 9/8/2024 | MICHAEL LOPEZ |
| Grading Pre-Inspection | Cleared | 9/8/2024 | MANUEL TEJADA |
| Roof/Waste drainage to street | Cleared | 9/18/2024 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 9/18/2024 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 9/19/2024 | LEE GUILBEAUX |
| Sewer availability | Cleared | 9/19/2024 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Alrayes,, Nidham Aram; Lic. No.: C65487 | 10346 SAMOA AVE TUJUNGA, CA 91042 |
| Engineer | Haddad,, Raymond M; Lic. No.: GE2985 | 17106 CEREDO PL GRANADA HILLS, CA 91344 |
| Engineer | Moradian,, Helbert; Lic. No.: C76618 | 6854 FOOTHILL BLVD TUJUNGA, CA 91042 |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/18/2025 | Not Ready for Inspection | WILLIAM WREN |
| Pre-Inspection | 4/18/2025 | Partial Inspection | WILLIAM WREN |
| Deputy Drilled-In Anchors | 6/13/2025 | Conditional Approval | RAUL OLAGI |
| Footing/Foundation/Slab | 7/9/2025 | Approved | MICHEL ABAJAN |
| Deputy Steel/Welding | 8/7/2025 | Conditional Approval | WILLIAM WREN |
| Deputy Steel/Welding | 8/11/2025 | Conditional Approval | DAVID MATSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/3/2025 | Partial Approval | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 10/7/2025 | Approved | KEVIN BERBERYAN |
| Green Building Rough | 11/10/2025 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 11/10/2025 | Partial Approval | MATTHEW NELSON |
| ELECTRICAL-Rough | 4/17/2026 | Approved | NICHOLAS TROWBRIDGE |
| HVAC-Rough | 4/17/2026 | Approved | NICHOLAS TROWBRIDGE |
| PLUMBING-Rough | 4/17/2026 | Approved | NICHOLAS TROWBRIDGE |
| BUILDING-Rough-Frame | 5/27/2026 | Approved | NICHOLAS TROWBRIDGE |
| Insulation | 6/9/2026 | Approved | NICHOLAS TROWBRIDGE |
| Interior/Exterior Lathing | 6/9/2026 | Approved | NICHOLAS TROWBRIDGE |
| Drywall Nailing | 7/8/2026 | Approved | NICHOLAS TROWBRIDGE |