1027 E NOWITA PL 90291

Certificate Information: 1027 E NOWITA PL 90291

Application / Permit
24014-20000-03646
Plan Check / Job No.
B24VN13415
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION TO AND CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 12/11/2024
Issuing Office
West Los Angeles
Current Status
CofO Issued on 7/8/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/16/2024 APPLICANT
Assigned to Plan Check Engineer 8/22/2024 JEROME MAGAT PALMA
Corrections Issued 8/23/2024 JEROME MAGAT PALMA
Building Plans Picked Up 8/27/2024 APPLICANT
Applicant returned to address corrections 10/22/2024 KAMYAR EMAMI
Applicant returned to address corrections 11/5/2024 ANGELICA DAVE
Applicant returned to address corrections 11/15/2024 KAMYAR EMAMI
Applicant returned to address corrections 11/26/2024 MOHAMMAD ESMAILI
Applicant returned to address corrections 12/9/2024 RICHARD GARCIA
Plan Check Approved 12/11/2024 JOHNPAUL ISIP
Issued 12/11/2024 APPLICANT
CofO in Progress 7/7/2025 DAVID FEILER
Permit Finaled 7/8/2025 RICHARD STEINBACH
CofO Issued 7/8/2025 RICHARD STEINBACH
Permit Finaled 7/8/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 9/23/2024 HISASHI KOBAYAKAWA
Roof/Waste drainage to street Cleared 9/23/2024 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 9/24/2024 HISASHI KOBAYAKAWA
Sewer availability Cleared 9/24/2024 HISASHI KOBAYAKAWA
Specific Plan Cleared 10/16/2024 RICHARD WOO

Contact Information

Contractor Liebobuilders; Lic. No.: 1054050-B 18401 BURBANK BLVD SUITE 120      TARZANA, CA 91356

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/12/2024 Partial Approval MICHAEL ALLEN
Sewer 12/12/2024 Not Ready for Inspection MICHAEL ALLEN
Excavation/Setback/Form/Re-Bar 12/16/2024 Corrections Issued HERBERT GIRON
Footing/Foundation/Slab 12/16/2024 Corrections Issued HERBERT GIRON
Sewer 12/16/2024 Partial Approval HERBERT GIRON
Special/Order Compliance 12/16/2024 Corrections Issued HERBERT GIRON
Footing/Foundation/Slab 12/23/2024 Approved JESUS RODRIGUEZ
Sewer 12/23/2024 Partial Approval JESUS RODRIGUEZ
Sewer 1/2/2025 Approved JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 1/14/2025 Corrections Issued TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 1/30/2025 Corrections Issued HERBERT GIRON
PLUMBING-Rough 1/30/2025 Approved HERBERT GIRON
BUILDING-Rough-Frame 2/21/2025 Not Ready for Inspection HERBERT GIRON
ELECTRICAL-Rough 2/21/2025 Corrections Issued HERBERT GIRON
Green Building Rough 2/21/2025 Not Ready for Inspection HERBERT GIRON
BUILDING-Rough-Frame 3/3/2025 Corrections Issued HERBERT GIRON
ELECTRICAL-Rough 3/3/2025 Approved HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 3/3/2025 Corrections Issued HERBERT GIRON
Green Building Rough 3/3/2025 Approved HERBERT GIRON
Interior/Exterior Lathing 3/3/2025 Partial Approval HERBERT GIRON
BUILDING-Rough-Frame 3/10/2025 Approved JESUS RODRIGUEZ
ELECTRICAL-Rough 3/10/2025 Approved JESUS RODRIGUEZ
HVAC-Rough 3/10/2025 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 3/10/2025 Approved JESUS RODRIGUEZ
Insulation 3/17/2025 Approved JESUS RODRIGUEZ
Shower Pan 3/17/2025 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 3/19/2025 Approved MICHAEL ALLEN
Drywall Nailing 3/26/2025 Approved JAYLIN GRAVITTE
ELECTRICAL-Final 6/30/2025 Approved JESUS RODRIGUEZ
Final 6/30/2025 Corrections Issued JESUS RODRIGUEZ
Green Building Final 6/30/2025 Approved JESUS RODRIGUEZ
HVAC-Final 6/30/2025 Approved JESUS RODRIGUEZ
PLUMBING-Final 6/30/2025 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 6/30/2025 SGSOV Not Required JESUS RODRIGUEZ
Service/Power Release 6/30/2025 Approved JESUS RODRIGUEZ
Smoke Detectors 6/30/2025 Approved JESUS RODRIGUEZ
Final 7/7/2025 OK to Issue CofO DAVID FEILER