11921 W KEARSARGE ST 90049
Certificate Information: 11921 W KEARSARGE ST 90049
- Application / Permit
- 24014-20000-03632
- Plan Check / Job No.
- B24VN13329
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL (E) SFD AND ADDITION TO FRONT AND BACK. ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 2/18/2025
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 2/18/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/15/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/21/2024 | ARTIN ZARUKIAN |
| Corrections Issued | 8/22/2024 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 8/29/2024 | APPLICANT |
| Applicant returned to address corrections | 10/4/2024 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 1/16/2025 | KAMYAR EMAMI |
| Applicant returned to address corrections | 1/24/2025 | ISIS ARGUETA |
| Plan Check Approved | 2/14/2025 | ARAMIK SHAHMIRZAIAN |
| Issued | 2/18/2025 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/26/2024 | DIANA RENTERIA |
| Roof/Waste drainage to street | Cleared | 8/26/2024 | DIANA RENTERIA |
| ZA Case | Cleared | 8/26/2024 | JACQUELINE TORRES |
| ZA Case | Cleared | 8/26/2024 | JACQUELINE TORRES |
| Specific Plan | Cleared | 1/28/2025 | HAMID GHAEMMAGHAMI |
| GPI Written Notices | Cleared | 2/14/2025 | KAMYAR EMAMI |
| Grading Pre-Inspection | Cleared | 2/14/2025 | ARTIN ZARUKIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Erdelyi,, Peter Tibor; Lic. No.: C26962 | 2999 OVERLAND AVE STE 103 LOS ANGELES, CA 90064 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/24/2025 | Partial Inspection | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 4/1/2025 | Partial Approval | HERBERT GIRON |
| Excavation/Setback/Form/Re-Bar | 6/23/2025 | Not Ready for Inspection | HERBERT GIRON |
| Footing/Foundation/Slab | 6/23/2025 | Not Ready for Inspection | HERBERT GIRON |
| Excavation/Setback/Form/Re-Bar | 6/27/2025 | Partial Approval | HERBERT GIRON |
| Footing/Foundation/Slab | 6/27/2025 | Partial Approval | HERBERT GIRON |
| PLUMBING-Rough | 7/11/2025 | Partial Approval | HERBERT GIRON |
| Underground Mechanical | 7/11/2025 | Partial Approval | HERBERT GIRON |
| Deputy Drilled-In Anchors | 7/22/2025 | Conditional Approval | HERBERT GIRON |
| Deputy Reinf. Concrete | 7/22/2025 | Conditional Approval | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 9/22/2025 | Partial Approval | HERBERT GIRON |
| Footing/Foundation/Slab | 9/22/2025 | Approved | HERBERT GIRON |
| HVAC-Rough | 10/17/2025 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Rough | 10/17/2025 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Rough | 10/23/2025 | Not Ready for Inspection | HERBERT GIRON |
| HVAC-Rough | 10/23/2025 | Approved | HERBERT GIRON |
| Gas Test | 10/27/2025 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Rough | 10/27/2025 | Not Ready for Inspection | HERBERT GIRON |
| ELECTRICAL-Rough | 11/5/2025 | Corrections Issued | HERBERT GIRON |
| Gas Test | 11/5/2025 | Approved | HERBERT GIRON |
| PLUMBING-Rough | 11/5/2025 | Approved | HERBERT GIRON |
| ELECTRICAL-Rough | 11/7/2025 | Partial Approval | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 11/7/2025 | Corrections Issued | HERBERT GIRON |
| Shower Pan | 11/7/2025 | Approved | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 11/14/2025 | Partial Approval | HERBERT GIRON |
| BUILDING-Rough-Frame | 11/20/2025 | Partial Approval | HERBERT GIRON |
| Green Building Rough | 11/20/2025 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 11/20/2025 | Partial Approval | HERBERT GIRON |
| Insulation | 12/2/2025 | Corrections Issued | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 1/15/2026 | Approved | HERBERT GIRON |
| ELECTRICAL-Rough | 1/15/2026 | Approved | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 1/15/2026 | Approved | HERBERT GIRON |
| Footing/Foundation/Slab | 1/15/2026 | Approved | HERBERT GIRON |
| Insulation | 1/23/2026 | Approved | HERBERT GIRON |
| Drywall Nailing | 2/13/2026 | Approved | HERBERT GIRON |
| Gas Test | 4/20/2026 | Corrections Issued | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 4/20/2026 | Approved | KEVIN SARGSYAN |
| Gas Test | 5/5/2026 | Not Ready for Inspection | KEVIN SARGSYAN |
| Service/Power Release | 5/5/2026 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 5/14/2026 | Approved | CARLOS MATAMOROS |