19167 W ALLANDALE DR 91356

Certificate Information: 19167 W ALLANDALE DR 91356

Application / Permit
24014-20000-03617
Plan Check / Job No.
B24VN13200
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 6'-6" x 23'-6" ADDITION AT REAR W/ BALCONY ABOVE
Permit Issued
Issued on 11/6/2024
Issuing Office
Valley
Current Status
CofO Issued on 4/18/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/15/2024 APPLICANT
Assigned to Plan Check Engineer 9/3/2024 SEAN SHAHMIRI
Corrections Issued 9/4/2024 SEAN SHAHMIRI
Quality Review Completed 9/6/2024 STEVEN KIM
Building Plans Picked Up 9/9/2024 APPLICANT
Applicant returned to address corrections 11/6/2024 SEAN SHAHMIRI
Plan Check Approved 11/6/2024 SEAN SHAHMIRI
Issued 11/6/2024 APPLICANT
CofO in Progress 1/6/2026 JOHN KIDWELL
Permit Finaled 4/18/2026 MICHAEL PELHAM
CofO Issued 4/18/2026 MICHAEL PELHAM
Permit Finaled 4/18/2026 MICHAEL PELHAM

Permit Application Clearance Information

Grading Pre-Inspection Cleared 10/17/2024 CHARLES POWELL
Eng Process Fee Ord 176,300 Cleared 10/30/2024 BIAINA HARITUNIAN
Miscellaneous Cleared 10/30/2024 NOAH MCCOY
Miscellaneous Cleared 10/30/2024 NOAH MCCOY
Miscellaneous Cleared 10/30/2024 NOAH MCCOY
Roof/Waste drainage to street Cleared 10/30/2024 BIAINA HARITUNIAN
ZA Case Cleared 10/30/2024 NOAH MCCOY
ZA Case Cleared 10/30/2024 NOAH MCCOY
ZA Case Cleared 10/30/2024 NOAH MCCOY
Watercourse Cleared 10/31/2024 BIAINA HARITUNIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Basma,, Ali J; Lic. No.: C53080 6047 TAMPA AVE   SUITE 304    TARZANA, CA 91356

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/20/2025 Partial Approval JOHN KIDWELL
Deputy Drilled-In Anchors 3/3/2025 Partial Approval JOHN KIDWELL
Footing/Foundation/Slab 3/4/2025 Conditional Approval JOHN KIDWELL
Deputy Reinf. Concrete 3/7/2025 Partial Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 3/19/2025 Partial Approval JOHN KIDWELL
ELECTRICAL-Rough 5/14/2025 Approved JOHN KIDWELL
HVAC-Rough 5/14/2025 Approved JOHN KIDWELL
PLUMBING-Rough 5/14/2025 Partial Approval JOHN KIDWELL
BUILDING-Rough-Frame 5/22/2025 Approved JOHN KIDWELL
Green Building Rough 5/22/2025 Approved JOHN KIDWELL
PLUMBING-Rough 5/22/2025 Approved JOHN KIDWELL
Drywall Nailing 6/3/2025 Approved MORRIS JACKSON
Insulation 6/3/2025 Approved MORRIS JACKSON
Final 11/21/2025 Corrections Issued JOHN KIDWELL
Footing/Foundation/Slab 11/21/2025 Approved JOHN KIDWELL
Green Building Final 11/21/2025 Not Ready for Inspection JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 11/21/2025 SGSOV Approved JOHN KIDWELL
Smoke Detectors 11/21/2025 Approved JOHN KIDWELL
Final 1/5/2026 OK to Issue CofO JOHN KIDWELL
Green Building Final 1/5/2026 Approved JOHN KIDWELL