14902 W HESBY ST 91403
Certificate Information: 14902 W HESBY ST 91403
- Application / Permit
- 24014-20000-03615
- Plan Check / Job No.
- B24VN13145
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD TO AND CONVERT (E) DET. GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 12/13/2024
- Issuing Office
- Current Status
- CofO Issued on 9/25/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/14/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/21/2024 | JESSE ARELLANO |
| Corrections Issued | 8/22/2024 | JESSE ARELLANO |
| Building Plans Picked Up | 8/27/2024 | APPLICANT |
| Applicant returned to address corrections | 12/5/2024 | GIOVANNY CHAVEZ |
| Plan Check Approved | 12/13/2024 | ANGELICA MARTINEZ |
| Issued | 12/13/2024 | APPLICANT |
| CofO in Progress | 9/17/2025 | JACK KARGODORIAN |
| CofO Issued | 9/25/2025 | RUBEN SALAS |
| Permit Finaled | 9/25/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 9/5/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 9/5/2024 | BIAINA HARITUNIAN |
| "Q" conditions | Cleared | 10/8/2024 | ASHLEY RODARTE |
| Eng Process Fee Ord 176,300 | Cleared | 10/8/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 10/8/2024 | BIAINA HARITUNIAN |
| ZI | Cleared | 10/8/2024 | ASHLEY RODARTE |
| Construction near power lines | Cleared | 12/4/2024 | TINA MIRANDA |
| Construction within easement | Cleared | 12/4/2024 | TINA MIRANDA |
Contact Information
| Contractor | Regal Landscaping & Construction Inc; Lic. No.: 1082611-B | 22647 VENTURA BLVD #618 WOODLAND HILLS, CA 91364 |
| Engineer | Mayorga,, Jose Aguinaldo; Lic. No.: C50322 | 20457 OREY PL WINNETKA, CA 91306 |
Inspector Information
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/23/2025 | Approved | JACK KARGODORIAN |
| Sewer | 2/24/2025 | Not Ready for Inspection | MICHAEL CORTEZ |
| PLUMBING-Rough | 2/25/2025 | Partial Approval | JACK KARGODORIAN |
| Footing/Foundation/Slab | 2/28/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| Footing/Foundation/Slab | 3/5/2025 | Approved | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/1/2025 | Partial Approval | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/7/2025 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 4/10/2025 | Partial Approval | MICHAEL CORTEZ |
| Rough-Elec/Plmb/HVAC | 5/5/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Rough-Elec/Plmb/HVAC | 5/19/2025 | Approved | JACK KARGODORIAN |
| Wood Frame | 5/21/2025 | Approved | JACK KARGODORIAN |
| Insulation | 5/27/2025 | Approved | JACK KARGODORIAN |
| Shower Pan | 5/27/2025 | Corrections Issued | JACK KARGODORIAN |
| Interior/Exterior Lathing | 5/30/2025 | Partial Approval | JACK KARGODORIAN |
| Shower Pan | 5/30/2025 | Approved | JACK KARGODORIAN |
| Drywall Nailing | 6/2/2025 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 6/2/2025 | Partial Approval | JACK KARGODORIAN |
| Sewer | 6/17/2025 | Partial Approval | JACK KARGODORIAN |
| Sewer | 6/20/2025 | Corrections Issued | JACK KARGODORIAN |
| Sewer | 6/24/2025 | Approved | JACK KARGODORIAN |
| Underground Mechanical | 7/17/2025 | Not Ready for Inspection | RYAN SALAZAR |
| Underground Mechanical | 7/22/2025 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 8/25/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Final | 8/25/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Final | 8/25/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Rough | 8/25/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 8/25/2025 | SGSOV Not Ready | MISAEL ESPARZA |
| Smoke Detectors | 8/25/2025 | Not Ready for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 9/5/2025 | Approved | JACK KARGODORIAN |
| Final | 9/5/2025 | Corrections Issued | JACK KARGODORIAN |
| Green Building Final | 9/5/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| Green Building Rough | 9/5/2025 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 9/5/2025 | SGSOV Not Ready | JACK KARGODORIAN |
| Smoke Detectors | 9/5/2025 | Approved | JACK KARGODORIAN |
| Final | 9/12/2025 | Corrections Issued | JACK KARGODORIAN |
| Green Building Final | 9/12/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 9/12/2025 | SGSOV Approved | JACK KARGODORIAN |
| Final | 9/17/2025 | OK to Issue CofO | JACK KARGODORIAN |
| Green Building Final | 9/17/2025 | Approved | JACK KARGODORIAN |