22732 W MARIANO ST 91367
Certificate Information: 22732 W MARIANO ST 91367
- Application / Permit
- 24014-20000-03609
- Plan Check / Job No.
- B24VN13119
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Remove (E) lattice roof at rear and addition to (E) SFD
- Permit Issued
- Issued on 8/27/2024
- Issuing Office
- Current Status
- CofO Issued on 9/11/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/14/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/16/2024 | SHANGQIN XIE |
| Corrections Issued | 8/17/2024 | SHANGQIN XIE |
| Plan Check Approved | 8/26/2024 | SHANGQIN XIE |
| Issued | 8/27/2024 | APPLICANT |
| CofO in Progress | 4/28/2025 | TROY SANDERS |
| No Progress | 8/28/2025 | ROBERT GOLD |
| CofO in Progress | 8/28/2025 | ROBERT GOLD |
| CofO in Progress | 8/28/2025 | ROBERT GOLD |
| No Progress | 9/10/2025 | ROBERT GOLD |
| CofO in Progress | 9/10/2025 | ROBERT GOLD |
| Permit Finaled | 9/11/2025 | JOHN JANSON |
| CofO Issued | 9/11/2025 | JOHN JANSON |
| Permit Finaled | 9/11/2025 | JOHN JANSON |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 8/19/2024 | RYAN CASTRO |
| Sewer availability | Cleared | 8/19/2024 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 8/20/2024 | RYAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Ebrahimian, Dehaghani, Mahdi; Lic. No.: C86987 | 19300 RINALDI ST, P.O. BOX 8401 PORTER RANCH, CA 91327 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/16/2024 | Conditional Approval | HENRY KIM |
| Footing/Foundation/Slab | 9/18/2024 | Approved | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 9/24/2024 | Partial Approval | TROY SANDERS |
| PLUMBING-Rough | 10/16/2024 | Off-Hour Fees Due | |
| PLUMBING-Rough | 10/17/2024 | Partial Approval | TROY SANDERS |
| PLUMBING-Rough | 10/28/2024 | Approved | TROY SANDERS |
| Deputy Drilled-In Anchors | 10/29/2024 | Partial Approval | SEAN WIRCH |
| BUILDING-Rough-Frame | 11/12/2024 | Approved | TROY SANDERS |
| MERV13>=Rough | 11/12/2024 | Approved | TROY SANDERS |
| Rough-Elec/Plmb/HVAC | 11/12/2024 | Approved | TROY SANDERS |
| PLUMBING-Rough | 11/20/2024 | Not Ready for Inspection | TROY SANDERS |
| Sewer | 11/20/2024 | Not Ready for Inspection | TROY SANDERS |
| PLUMBING-Rough | 11/21/2024 | Not Ready for Inspection | TROY SANDERS |
| Sewer | 11/21/2024 | Not Ready for Inspection | TROY SANDERS |
| ELECTRICAL-Rough | 11/26/2024 | Approved | TROY SANDERS |
| ELECTRICAL-Final | 11/27/2024 | Not Ready for Inspection | TROY SANDERS |
| PLUMBING-Final | 11/27/2024 | Not Ready for Inspection | TROY SANDERS |
| Interior/Exterior Lathing | 12/2/2024 | Partial Approval | TROY SANDERS |
| Insulation | 12/4/2024 | Approved | TROY SANDERS |
| Drywall Nailing | 12/18/2024 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 12/18/2024 | Partial Approval | TROY SANDERS |
| Service/Power Release | 1/10/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| Service/Power Release | 1/14/2025 | Approved | TROY SANDERS |
| ELECTRICAL-Final | 4/15/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| HVAC-Final | 4/15/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| PLUMBING-Final | 4/15/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| Final | 4/25/2025 | Partial Approval | TROY SANDERS |
| MERV13>=Final | 4/25/2025 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 4/25/2025 | SGSOV Approved | TROY SANDERS |
| Smoke Detectors | 4/25/2025 | Approved | TROY SANDERS |