15032 W MINNEHAHA ST 91345
Certificate Information: 15032 W MINNEHAHA ST 91345
- Application / Permit
- 24014-20000-03607
- Plan Check / Job No.
- B24VN13083
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING DETACHED GARAGE AND NEW ADDITION TO NEW ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). REMOVE EXISTING ATTACHED TOOL SHED. WORK DONE PER WFPP AND ENGINEER DETAIL.
- Permit Issued
- Issued on 11/22/2024
- Issuing Office
- Current Status
- CofO Issued on 12/31/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/13/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/19/2024 | JESSE ARELLANO |
| Corrections Issued | 8/20/2024 | JESSE ARELLANO |
| Building Plans Picked Up | 8/21/2024 | APPLICANT |
| Plan Check Approved | 11/21/2024 | MADISON O'DELL |
| Plan Check Approved | 11/21/2024 | MADISON O'DELL |
| Issued | 11/22/2024 | APPLICANT |
| CofO in Progress | 12/24/2025 | JENNIFER RABUCHIN |
| Permit Finaled | 12/31/2025 | RUBEN SALAS |
| CofO Issued | 12/31/2025 | RUBEN SALAS |
| Permit Finaled | 12/31/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 8/21/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 8/21/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 8/22/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 8/22/2024 | BIAINA HARITUNIAN |
| Construction near power lines | Cleared | 11/19/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Gas Test | 2/25/2025 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 2/25/2025 | Partial Approval | JENNIFER RABUCHIN |
| Sewer | 2/25/2025 | Approved | JENNIFER RABUCHIN |
| Deputy Drilled-In Anchors | 3/6/2025 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 3/12/2025 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 4/7/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Pre-Inspection | 4/11/2025 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 5/9/2025 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Rough | 5/9/2025 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 5/13/2025 | Approved | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 5/13/2025 | Partial Approval | JENNIFER RABUCHIN |
| Green Building Rough | 5/13/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 6/16/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 8/6/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 8/11/2025 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 8/11/2025 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 8/11/2025 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 8/11/2025 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 8/11/2025 | Approved | JENNIFER RABUCHIN |
| Insulation | 8/18/2025 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 8/22/2025 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 10/10/2025 | Approved | MICHAEL CORTEZ |
| Final | 12/15/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 12/15/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 12/15/2025 | SGSOV Not Ready | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 12/15/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Final | 12/23/2025 | Approved | JENNIFER RABUCHIN |
| Final | 12/23/2025 | OK to Issue CofO | JENNIFER RABUCHIN |
| Green Building Final | 12/23/2025 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 12/23/2025 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 12/23/2025 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 12/23/2025 | SGSOV Approved | JENNIFER RABUCHIN |
| Service/Power Release | 12/23/2025 | Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 12/23/2025 | Approved | JENNIFER RABUCHIN |