15032 W MINNEHAHA ST 91345

Certificate Information: 15032 W MINNEHAHA ST 91345

Application / Permit
24014-20000-03607
Plan Check / Job No.
B24VN13083
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DETACHED GARAGE AND NEW ADDITION TO NEW ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). REMOVE EXISTING ATTACHED TOOL SHED. WORK DONE PER WFPP AND ENGINEER DETAIL.
Permit Issued
Issued on 11/22/2024
Issuing Office
Current Status
CofO Issued on 12/31/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/13/2024 APPLICANT
Assigned to Plan Check Engineer 8/19/2024 JESSE ARELLANO
Corrections Issued 8/20/2024 JESSE ARELLANO
Building Plans Picked Up 8/21/2024 APPLICANT
Plan Check Approved 11/21/2024 MADISON O'DELL
Plan Check Approved 11/21/2024 MADISON O'DELL
Issued 11/22/2024 APPLICANT
CofO in Progress 12/24/2025 JENNIFER RABUCHIN
Permit Finaled 12/31/2025 RUBEN SALAS
CofO Issued 12/31/2025 RUBEN SALAS
Permit Finaled 12/31/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 8/21/2024 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 8/21/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 8/22/2024 BIAINA HARITUNIAN
Sewer availability Cleared 8/22/2024 BIAINA HARITUNIAN
Construction near power lines Cleared 11/19/2024 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Gas Test 2/25/2025 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 2/25/2025 Partial Approval JENNIFER RABUCHIN
Sewer 2/25/2025 Approved JENNIFER RABUCHIN
Deputy Drilled-In Anchors 3/6/2025 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 3/12/2025 Approved MICHEL ABAJAN
PLUMBING-Rough 4/7/2025 Corrections Issued JENNIFER RABUCHIN
Pre-Inspection 4/11/2025 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 5/9/2025 Corrections Issued JENNIFER RABUCHIN
HVAC-Rough 5/9/2025 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 5/13/2025 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 5/13/2025 Partial Approval JENNIFER RABUCHIN
Green Building Rough 5/13/2025 Not Ready for Inspection JENNIFER RABUCHIN
ELECTRICAL-Rough 6/16/2025 Corrections Issued JENNIFER RABUCHIN
Interior/Exterior Lathing 8/6/2025 Corrections Issued CHRISTOPHER ROJAS
BUILDING-Rough-Frame 8/11/2025 Approved JENNIFER RABUCHIN
Green Building Rough 8/11/2025 Approved JENNIFER RABUCHIN
HVAC-Rough 8/11/2025 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 8/11/2025 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 8/11/2025 Approved JENNIFER RABUCHIN
Insulation 8/18/2025 Approved JENNIFER RABUCHIN
Drywall Nailing 8/22/2025 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 10/10/2025 Approved MICHAEL CORTEZ
Final 12/15/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Final 12/15/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 12/15/2025 SGSOV Not Ready ROBERTO PALACIOS-LOPEZ
Smoke Detectors 12/15/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 12/23/2025 Approved JENNIFER RABUCHIN
Final 12/23/2025 OK to Issue CofO JENNIFER RABUCHIN
Green Building Final 12/23/2025 Approved JENNIFER RABUCHIN
HVAC-Final 12/23/2025 Approved JENNIFER RABUCHIN
PLUMBING-Final 12/23/2025 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 12/23/2025 SGSOV Approved JENNIFER RABUCHIN
Service/Power Release 12/23/2025 Approved JENNIFER RABUCHIN
Smoke Detectors 12/23/2025 Approved JENNIFER RABUCHIN