6200 N CAMELLIA AVE 91606

Certificate Information: 6200 N CAMELLIA AVE 91606

Application / Permit
24014-20000-03594
Plan Check / Job No.
B24VN12986
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: INTERIOR REMODEL WITH ADDITION TO (E) SFD
Permit Issued
Issued on 3/10/2025
Issuing Office
Current Status
CofO Issued on 6/17/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/16/2024 APPLICANT
Assigned to Plan Check Engineer 8/22/2024 MARCELA FRANQUEZ
Corrections Issued 8/24/2024 MARCELA FRANQUEZ
Quality Review Completed 9/4/2024 TU HUA
Applicant returned to address corrections 12/11/2024 MARCELA FRANQUEZ
Applicant returned to address corrections 12/24/2024 MARCELA FRANQUEZ
Plan Check Approved 1/23/2025 MARCELA FRANQUEZ
Issued 3/10/2025 APPLICANT
CofO in Progress 5/22/2026 ROBERTO PALACIOS-LOPEZ
Permit Finaled 6/17/2026 RUBEN SALAS
CofO Issued 6/17/2026 RUBEN SALAS
Permit Finaled 6/17/2026 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 9/4/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 9/5/2024 BIAINA HARITUNIAN
Sewer availability Cleared 9/5/2024 BIAINA HARITUNIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 11 CEDARWOOD DR      POMONA, CA 91766

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/1/2025 Conditional Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 8/1/2025 Corrections Issued JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 8/5/2025 Not Ready for Inspection JOSE AVILA
Wood Frame 8/8/2025 Partial Approval JOSE AVILA
PLUMBING-Rough 8/12/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 8/12/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 10/30/2025 Corrections Issued JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 11/10/2025 Partial Approval JOSE AVILA
HVAC-Rough 11/17/2025 Not Ready for Inspection JOSE AVILA
Special/Order Compliance 11/24/2025 Corrections Issued JOSE AVILA
PLUMBING-Rough 11/25/2025 Not Ready for Inspection JOSE AVILA
Special/Order Compliance 12/2/2025 Corrections Issued JOSE AVILA
Special/Order Compliance 12/2/2025 Partial Inspection JUAN VALENZUELA
HVAC-Rough 12/4/2025 Approved JOSE AVILA
Deputy Wood Construction 12/5/2025 Conditional Approval JUAN VALENZUELA
ELECTRICAL-Rough 12/5/2025 Approved JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 12/10/2025 Approved JOSE AVILA
Interior/Exterior Lathing 12/16/2025 Approved JOSE AVILA
PLUMBING-Rough 12/16/2025 Approved JOSE AVILA
Insulation 12/22/2025 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 1/8/2026 Approved JOSE AVILA
Interior/Exterior Lathing 1/8/2026 Approved JOSE AVILA
Insulation 1/12/2026 Approved JOSE AVILA
BUILDING-Rough-Frame 2/4/2026 Approved ROBERTO PALACIOS-LOPEZ
Drywall Nailing 2/4/2026 Approved ROBERTO PALACIOS-LOPEZ
Green Building Rough 2/4/2026 Approved ROBERTO PALACIOS-LOPEZ
Gas Test 2/10/2026 Approved ROBERTO PALACIOS-LOPEZ
Sewer 2/10/2026 Approved ROBERTO PALACIOS-LOPEZ
Underground Mechanical 2/10/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 4/23/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 4/23/2026 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Green Building Final 4/23/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 4/23/2026 SGSOV Approved ROBERTO PALACIOS-LOPEZ
Smoke Detectors 4/23/2026 Approved ROBERTO PALACIOS-LOPEZ
Underground Mechanical 4/23/2026 Approved ROBERTO PALACIOS-LOPEZ
Final 5/19/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 5/19/2026 Approved ROBERTO PALACIOS-LOPEZ
Green Building Final 5/19/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 5/22/2026 OK to Issue CofO ROBERTO PALACIOS-LOPEZ
Green Building Final 5/22/2026 Approved ROBERTO PALACIOS-LOPEZ
Service/Power Release 5/22/2026 Approved ROBERTO PALACIOS-LOPEZ