6509 N BEN AVE 91606

Certificate Information: 6509 N BEN AVE 91606

Application / Permit
24014-20000-03579
Plan Check / Job No.
B24VN12897
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Addition and conversion of the garage to new 42' 7" x 28' 10" ADU per LAMC 12.22 A.33(c)* and (d)*. NFPA 13D sprinkler required. All work done per engineer.
Permit Issued
Issued on 9/13/2024
Issuing Office
Current Status
CofO Issued on 10/28/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/12/2024 APPLICANT
Assigned to Plan Check Engineer 8/15/2024 NAREG ATARIAN
Corrections Issued 8/18/2024 NAREG ATARIAN
Quality Review Completed 8/21/2024 OMID HEDAYAT
Building Plans Picked Up 8/21/2024 APPLICANT
Plan Check Approved 9/13/2024 NAREG ATARIAN
Issued 9/13/2024 APPLICANT
CofO in Progress 9/26/2025 ROBERTO PALACIOS-LOPEZ
CofO Issued 10/28/2025 RUBEN SALAS
Permit Finaled 10/28/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 8/19/2024 RYAN CASTRO
Roof/Waste drainage to street Cleared 8/19/2024 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 8/22/2024 EDGAR ALCARAZ
Sewer availability Cleared 8/22/2024 EDGAR ALCARAZ

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/9/2024 Partial Approval JOSE AVILA
Footing/Foundation/Slab 10/16/2024 Approved JOSE AVILA
Deputy Drilled-In Anchors 10/22/2024 Conditional Approval JOSE AVILA
Pre-Inspection 10/22/2024 Corrections Issued JOSE AVILA
Excavation/Setback/Form/Re-Bar 11/5/2024 Approved JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 11/19/2024 Corrections Issued JOSE AVILA
PLUMBING-Rough 12/23/2024 Approved MISAEL ESPARZA
HVAC-Rough 12/27/2024 Corrections Issued JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 1/3/2025 Partial Approval JOSE AVILA
ELECTRICAL-Rough 1/13/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Rough 1/13/2025 Approved ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 1/17/2025 Approved ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 1/17/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 1/27/2025 Partial Approval ROBERTO PALACIOS-LOPEZ
Green Building Rough 1/27/2025 Approved ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 2/4/2025 Approved ROBERTO PALACIOS-LOPEZ
Insulation 2/4/2025 Approved ROBERTO PALACIOS-LOPEZ
Drywall Nailing 2/25/2025 Approved MICHAEL CORTEZ
Sewer 2/28/2025 Approved ROBERTO PALACIOS-LOPEZ
Shower Pan 2/28/2025 Approved ROBERTO PALACIOS-LOPEZ
Underground Mechanical 2/28/2025 Approved ROBERTO PALACIOS-LOPEZ
Shower Pan 3/4/2025 No Access for Inspection MICHAEL CORTEZ
Shower Pan 3/6/2025 Approved ROBERTO PALACIOS-LOPEZ
Final 9/2/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Final 9/2/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 9/2/2025 SGSOV Approved ROBERTO PALACIOS-LOPEZ
Smoke Detectors 9/2/2025 Approved ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 9/19/2025 Approved ROBERTO PALACIOS-LOPEZ
Final 9/19/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Gas Test 9/19/2025 Approved ROBERTO PALACIOS-LOPEZ
Green Building Final 9/19/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Final 9/19/2025 Approved ROBERTO PALACIOS-LOPEZ
PLUMBING-Final 9/19/2025 Approved ROBERTO PALACIOS-LOPEZ
Service/Power Release 9/19/2025 Approved ROBERTO PALACIOS-LOPEZ
Final 9/26/2025 OK to Issue CofO ROBERTO PALACIOS-LOPEZ
Green Building Final 9/26/2025 Approved ROBERTO PALACIOS-LOPEZ