6449-6451 N GERALD AVE 91406

Certificate Information: 6449-6451 N GERALD AVE 91406

Application / Permit
24014-20000-03561
Plan Check / Job No.
B24VN10188
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION OF (N) 1-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)(e) TO (E) 1-STORY SFD (NFPA-13D FIRE SPRINKLERS THROUGHOUT) **ePlan**
Permit Issued
Issued on 2/7/2025
Issuing Office
Current Status
CofO in Progress on 4/14/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/19/2024 APPLICANT
Assigned to Plan Check Engineer 8/8/2024 NILOOFAR MEHRAIN
Corrections Issued 8/11/2024 NILOOFAR MEHRAIN
Quality Review Completed 8/14/2024 JASON HEALEY
Plan Check Approved 11/5/2024 NILOOFAR MEHRAIN
Issued 2/7/2025 APPLICANT
CofO in Progress 3/24/2026 KIRK SANDERS
No Progress 4/14/2026 JOSE AVILA
CofO in Progress 4/14/2026 JOSE AVILA

Permit Application Clearance Information

Address approval Cleared 8/15/2024 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 8/15/2024 RYAN CASTRO
Roof/Waste drainage to street Cleared 8/15/2024 RYAN CASTRO
ZI Cleared 8/22/2024 ASHLEY RODARTE
Sewer availability Cleared 9/12/2024 RYAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 11 CEDARWOOD DR      POMONA, CA 91766

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/20/2025 Conditional Approval RAUL OLAGI
Excavation/Setback/Form/Re-Bar 4/4/2025 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 4/4/2025 Not Ready for Inspection MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 4/8/2025 Corrections Issued SALVADOR MARTINEZ
Footing/Foundation/Slab 4/8/2025 Corrections Issued SALVADOR MARTINEZ
Excavation/Setback/Form/Re-Bar 4/22/2025 Approved SALVADOR MARTINEZ
Footing/Foundation/Slab 4/22/2025 Approved SALVADOR MARTINEZ
BUILDING-Rough-Frame 5/14/2025 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Rough 5/22/2025 Partial Approval MISAEL ESPARZA
Wood Frame 5/22/2025 Partial Approval MISAEL ESPARZA
Footing/Foundation/Slab 5/29/2025 Approved GAREN HAYRAPETYAN
Insulation 5/29/2025 Partial Approval GAREN HAYRAPETYAN
Floor/Roof Diaphrgm/Shear Wall 6/5/2025 Partial Approval JOAQUIN GREENOUGH
PLUMBING-Rough 7/28/2025 Approved KEVIN BERBERYAN
HVAC-Rough 7/30/2025 Corrections Issued SALVADOR MARTINEZ
ELECTRICAL-Rough 8/6/2025 Corrections Issued MATTHEW NELSON
HVAC-Rough 8/11/2025 Not Ready for Inspection GAREN HAYRAPETYAN
Shower Pan 8/11/2025 Approved GAREN HAYRAPETYAN
Special/Order Compliance 8/11/2025 Corrections Issued GAREN HAYRAPETYAN
HVAC-Rough 8/25/2025 Corrections Issued WAYNE REGESTER
HVAC-Rough 9/3/2025 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 9/8/2025 Approved WAYNE REGESTER
HVAC-Rough 9/8/2025 Corrections Issued WAYNE REGESTER
Wood Frame 9/8/2025 Partial Approval WAYNE REGESTER
Wood Frame 9/10/2025 Not Ready for Inspection WAYNE REGESTER
ELECTRICAL-Rough 9/16/2025 Approved GAREN HAYRAPETYAN
HVAC-Rough 9/16/2025 Approved GAREN HAYRAPETYAN
PLUMBING-Rough 9/16/2025 Approved GAREN HAYRAPETYAN
Wood Frame 9/25/2025 Partial Approval NICHOLAS TROWBRIDGE
Wood Frame 10/1/2025 Approved GAREN HAYRAPETYAN
Interior/Exterior Lathing 10/2/2025 Not Ready for Inspection JOSE AVILA
Interior/Exterior Lathing 10/8/2025 Approved LOUIS ESCOTO
Insulation 10/21/2025 Approved GAREN HAYRAPETYAN
Drywall Nailing 10/27/2025 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 1/16/2026 Approved GAREN HAYRAPETYAN
Final 1/16/2026 Corrections Issued GAREN HAYRAPETYAN
Green Building Final 1/16/2026 Approved GAREN HAYRAPETYAN
Green Building Rough 1/16/2026 Approved GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 1/16/2026 SGSOV Not Ready GAREN HAYRAPETYAN
Smoke Detectors 1/16/2026 Approved GAREN HAYRAPETYAN
ELECTRICAL-Final 3/9/2026 Corrections Issued KIRK SANDERS
Final 3/9/2026 Corrections Issued KIRK SANDERS
HVAC-Final 3/9/2026 Approved KIRK SANDERS
PLUMBING-Final 3/9/2026 Approved KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 3/9/2026 SGSOV Approved KIRK SANDERS
Final 3/17/2026 Partial Approval KIRK SANDERS
ELECTRICAL-Final 3/23/2026 Approved KIRK SANDERS
Final 3/23/2026 OK to Issue CofO KIRK SANDERS
HVAC-Final 3/23/2026 Approved KIRK SANDERS
PLUMBING-Final 3/23/2026 Approved KIRK SANDERS
Service/Power Release 3/23/2026 Approved KIRK SANDERS
Special/Order Compliance 4/14/2026 Corrections Issued JOSE AVILA
Special/Order Compliance 6/9/2026 Partial Inspection JOSE AVILA