6600 N BABCOCK AVE 91606
Certificate Information: 6600 N BABCOCK AVE 91606
- Application / Permit
- 24014-20000-03555
- Plan Check / Job No.
- B24VN12697
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: IRREGULAR SHAPED ADDITION TO AND CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c), (d), and (g) WITH ATTACHED CARPORT.
- Permit Issued
- Issued on 1/24/2025
- Issuing Office
- Current Status
- CofO Issued on 7/10/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/9/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/13/2024 | OMAR GARNICA |
| Corrections Issued | 8/14/2024 | OMAR GARNICA |
| Applicant returned to address corrections | 10/26/2024 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 1/14/2025 | MOHAMMAD ESMAILI |
| Plan Check Approved | 1/21/2025 | MOHAMMAD ESMAILI |
| Issued | 1/24/2025 | APPLICANT |
| CofO in Progress | 6/25/2025 | GAREN HAYRAPETYAN |
| Permit Finaled | 7/10/2025 | RUBEN SALAS |
| Permit Finaled | 7/10/2025 | RUBEN SALAS |
| CofO Issued | 7/10/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 8/20/2024 | DIANA RENTERIA |
| Roof/Waste drainage to street | Cleared | 8/20/2024 | DIANA RENTERIA |
| Eng Process Fee Ord 176,300 | Cleared | 8/21/2024 | MARKOS PEREZ-BRAN |
| Sewer availability | Cleared | 8/21/2024 | MARKOS PEREZ-BRAN |
| Construction near power lines | Cleared | 1/8/2025 | THERESA NGUYEN |
Contact Information
| Contractor | Incan Builder; Lic. No.: 1082704-B | , |
| Engineer | Yenjai,, Seree; Lic. No.: C73151 | 3249 SHADYLAWN DRIVE DUARTE, CA 91010 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/28/2025 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Drilled-In Anchors | 1/30/2025 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 2/3/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Footing/Foundation/Slab | 2/4/2025 | Approved | GAREN HAYRAPETYAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/27/2025 | Approved | GAREN HAYRAPETYAN |
| Green Building Rough | 2/27/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Deputy Wood Construction | 3/5/2025 | Conditional Approval | ROBERT GOLD |
| ELECTRICAL-Rough | 3/7/2025 | Approved | GAREN HAYRAPETYAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/7/2025 | Approved | GAREN HAYRAPETYAN |
| PLUMBING-Rough | 3/7/2025 | Approved | GAREN HAYRAPETYAN |
| Special/Order Compliance | 3/7/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Green Building Rough | 3/21/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| HVAC-Rough | 3/21/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 3/25/2025 | Approved | OGANES TARAKHCHYAN |
| Green Building Rough | 3/25/2025 | Approved | OGANES TARAKHCHYAN |
| HVAC-Rough | 3/25/2025 | Approved | OGANES TARAKHCHYAN |
| Insulation | 4/2/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Interior/Exterior Lathing | 4/2/2025 | Partial Approval | GAREN HAYRAPETYAN |
| Insulation | 4/7/2025 | Approved | GAREN HAYRAPETYAN |
| Drywall Nailing | 4/10/2025 | Approved | GAREN HAYRAPETYAN |
| ELECTRICAL-Final | 6/10/2025 | Corrections Issued | MICHEL ABAJAN |
| Final | 6/17/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| Green Building Final | 6/17/2025 | Approved | GAREN HAYRAPETYAN |
| HVAC-Final | 6/17/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| PLUMBING-Final | 6/17/2025 | Corrections Issued | GAREN HAYRAPETYAN |
| SGSOV-Seismic Gas S/O Valve | 6/17/2025 | SGSOV Not Ready | GAREN HAYRAPETYAN |
| Smoke Detectors | 6/17/2025 | Approved | GAREN HAYRAPETYAN |
| Final | 6/25/2025 | OK to Issue CofO | GAREN HAYRAPETYAN |
| SGSOV-Seismic Gas S/O Valve | 6/25/2025 | SGSOV Approved | GAREN HAYRAPETYAN |