10006-10008 N MEMORY PARK AVE 91345
Certificate Information: 10006-10008 N MEMORY PARK AVE 91345
- Application / Permit
- 24014-20000-03547
- Plan Check / Job No.
- B24VN12637
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: Addition and convertion of (e) attached garage to ADU Per Ordinance and LAMC 12.22 A33(c)&(e).
- Permit Issued
- Issued on 9/22/2024
- Issuing Office
- Current Status
- CofO Issued on 9/4/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/9/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/14/2024 | ZAW HAN |
| Corrections Issued | 8/15/2024 | ZAW HAN |
| Applicant returned to address corrections | 8/31/2024 | NGHI SU |
| Applicant returned to address corrections | 9/6/2024 | NGHI SU |
| Plan Check Approved | 9/15/2024 | NGHI SU |
| Issued | 9/22/2024 | APPLICANT |
| CofO in Progress | 8/22/2025 | JENNIFER RABUCHIN |
| Permit Finaled | 9/4/2025 | RUBEN SALAS |
| CofO Issued | 9/4/2025 | RUBEN SALAS |
| Permit Finaled | 9/4/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 8/15/2024 | RYAN CASTRO |
| Roof/Waste drainage to street | Cleared | 8/15/2024 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 8/27/2024 | RYAN CASTRO |
| Sewer availability | Cleared | 8/27/2024 | RYAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/29/2025 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 1/29/2025 | Partial Approval | JENNIFER RABUCHIN |
| Sewer | 1/29/2025 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 2/11/2025 | Partial Approval | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 2/13/2025 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 2/18/2025 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 2/24/2025 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Rough | 2/24/2025 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 2/24/2025 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 2/24/2025 | Approved | JENNIFER RABUCHIN |
| Insulation | 2/27/2025 | Approved | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 3/3/2025 | Approved | JENNIFER RABUCHIN |
| Drywall Nailing | 3/6/2025 | Approved | LOUIS ESCOTO |
| BUILDING-Rough-Frame | 7/16/2025 | Approved | JENNIFER RABUCHIN |
| Final | 7/16/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Gas Test | 7/16/2025 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 7/16/2025 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 7/16/2025 | Approved | JENNIFER RABUCHIN |
| Final | 7/24/2025 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 8/22/2025 | Approved | JENNIFER RABUCHIN |
| Final | 8/22/2025 | OK to Issue CofO | JENNIFER RABUCHIN |
| Green Building Final | 8/22/2025 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 8/22/2025 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 8/22/2025 | Partial Inspection | JENNIFER RABUCHIN |
| Service/Power Release | 8/22/2025 | Approved | JENNIFER RABUCHIN |