Permit Issued
Issued on 10/14/2024
Issuing Office
Current Status
CofO Issued on 12/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/9/2024 APPLICANT
Assigned to Plan Check Engineer 8/14/2024 FERNANDO FLORES
Corrections Issued 8/15/2024 FERNANDO FLORES
Plan Check Approved 10/10/2024 ADAM HEGAZI
Issued 10/14/2024 APPLICANT
CofO in Progress 12/1/2025 MICHEL ABAJAN
Permit Finaled 12/18/2025 RUBEN SALAS
CofO Issued 12/18/2025 RUBEN SALAS
Permit Finaled 12/18/2025 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 8/15/2024 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 8/20/2024 RYAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Ebrahimi,, Amirhosin; Lic. No.: C92049 8619 RESEDA BLVD UNIT 304B      NORTHRIDGE, CA 91324

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/17/2025 Approved MICHEL ABAJAN
METHANE-Barrier 4/17/2025 Approved MICHEL ABAJAN
METHANE-Subgrade 4/17/2025 Approved MICHEL ABAJAN
PLUMBING-Rough 4/17/2025 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 6/24/2025 Approved MICHEL ABAJAN
ELECTRICAL-Rough 6/24/2025 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 6/24/2025 Partial Approval MICHEL ABAJAN
Green Building Rough 6/24/2025 Approved MICHEL ABAJAN
METHANE-Rough 6/24/2025 Approved MICHEL ABAJAN
PLUMBING-Rough 6/24/2025 Approved MICHEL ABAJAN
HVAC-Rough 6/25/2025 Not Ready for Inspection MICHEL ABAJAN
HVAC-Rough 7/3/2025 Approved MICHEL ABAJAN
Insulation 7/3/2025 Approved MICHEL ABAJAN
Shower Pan 7/3/2025 Approved MICHEL ABAJAN
Drywall Nailing 8/1/2025 Approved MICHEL ABAJAN
ELECTRICAL-Final 10/31/2025 Approved MICHEL ABAJAN
Final 10/31/2025 Corrections Issued MICHEL ABAJAN
Green Building Final 10/31/2025 Approved MICHEL ABAJAN
HVAC-Final 10/31/2025 Approved MICHEL ABAJAN
PLUMBING-Final 10/31/2025 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 10/31/2025 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 10/31/2025 Approved MICHEL ABAJAN
Final 11/6/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Final 11/26/2025 OK to Issue CofO MICHEL ABAJAN