4839 N SYLMAR AVE 91423

Certificate Information: 4839 N SYLMAR AVE 91423

Application / Permit
24014-20000-03525
Plan Check / Job No.
B24VN12491
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(C) AND (D) AND ADDITION OF 13'-9" x 12'-9". ALL WORK PER ENGINEERING
Permit Issued
Issued on 11/8/2024
Issuing Office
Valley
Current Status
CofO Issued on 8/5/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/8/2024 APPLICANT
Assigned to Plan Check Engineer 8/15/2024 ARAMIK SHAHMIRZAIAN
Corrections Issued 8/15/2024 ARAMIK SHAHMIRZAIAN
Building Plans Picked Up 8/16/2024 APPLICANT
Plan Check Approved 8/30/2024 SARKIS HARABEDIAN
Issued 11/8/2024 APPLICANT
CofO in Progress 7/16/2025 MISAEL ESPARZA
Permit Finaled 8/5/2025 RUBEN SALAS
CofO Issued 8/5/2025 RUBEN SALAS
Permit Finaled 8/5/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 8/19/2024 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 8/19/2024 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 8/19/2024 LEE GUILBEAUX
Sewer availability Cleared 8/19/2024 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 8/19/2024 LEE GUILBEAUX

Contact Information

Contractor New Generation Home Improvements Inc; Lic. No.: 938552-B 5805 WHITE OAK AVE #18431      ENCINO, CA 91416
Engineer Christiansen,, Scott; Lic. No.: C37989 1003 WILSHIRE BLVD 202      SANTA MONICA, CA 90401

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/22/2024 Corrections Issued KEVIN BERBERYAN
BUILDING-Rough-Frame 2/20/2025 Not Ready for Inspection MISAEL ESPARZA
ELECTRICAL-Rough 2/20/2025 Corrections Issued MISAEL ESPARZA
Green Building Rough 2/20/2025 Not Ready for Inspection MISAEL ESPARZA
HVAC-Rough 2/20/2025 Corrections Issued MISAEL ESPARZA
MERV13>=Rough 2/20/2025 Approved MISAEL ESPARZA
PLUMBING-Rough 2/20/2025 Partial Approval MISAEL ESPARZA
BUILDING-Rough-Frame 2/27/2025 Approved MISAEL ESPARZA
ELECTRICAL-Rough 2/27/2025 Conditional Approval MISAEL ESPARZA
Green Building Rough 2/27/2025 Not Ready for Inspection MISAEL ESPARZA
HVAC-Rough 2/27/2025 Approved MISAEL ESPARZA
PLUMBING-Rough 2/27/2025 Approved MISAEL ESPARZA
Gas Test 3/4/2025 Approved MICHAEL CORTEZ
Interior/Exterior Lathing 3/20/2025 Partial Approval MISAEL ESPARZA
Insulation 4/1/2025 Approved MISAEL ESPARZA
Shower Pan 4/1/2025 Approved MISAEL ESPARZA
Drywall Nailing 4/8/2025 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 6/12/2025 Approved MISAEL ESPARZA
Final 6/12/2025 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 6/12/2025 Approved MISAEL ESPARZA
Green Building Final 6/12/2025 Not Ready for Inspection MISAEL ESPARZA
Green Building Rough 6/12/2025 Approved MISAEL ESPARZA
MERV13>=Final 6/12/2025 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 6/12/2025 SGSOV Approved MISAEL ESPARZA
Smoke Detectors 6/12/2025 Corrections Issued MISAEL ESPARZA
Final 6/17/2025 OK to Issue CofO MISAEL ESPARZA
Green Building Final 6/17/2025 Approved MISAEL ESPARZA
Smoke Detectors 6/17/2025 Approved MISAEL ESPARZA