2953 S BEVERWIL DR 90034

Certificate Information: 2953 S BEVERWIL DR 90034

Application / Permit
24014-20000-03514
Plan Check / Job No.
B24VN12460
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION AND REMODEL TO (E) SFD. 1ST FLOOR INT REMODEL AND ADDITION. (N) 2ND FLOOR ADDITION. NFPA 13D FIRE SPRINKLERS THROUGHTOUT. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 10/30/2024
Issuing Office
Valley
Current Status
CofO Issued on 11/8/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/8/2024 APPLICANT
Assigned to Plan Check Engineer 8/22/2024 RAPHAEL ROSAS
Corrections Issued 8/29/2024 RAPHAEL ROSAS
Quality Review Completed 9/4/2024 STEVEN KIM
Building Plans Picked Up 9/5/2024 APPLICANT
Plan Check Approved 10/30/2024 RAPHAEL ROSAS
Issued 10/30/2024 APPLICANT
CofO in Progress 10/30/2025 MICHAEL ALLEN
Permit Finaled 11/8/2025 RICHARD STEINBACH
CofO Issued 11/8/2025 RICHARD STEINBACH
Permit Finaled 11/8/2025 RICHARD STEINBACH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/17/2024 LIAM ODONOVAN
Sewer availability Cleared 9/17/2024 LIAM ODONOVAN
Specific Plan Cleared 9/19/2024 HAMID GHAEMMAGHAMI
Roof/Waste drainage to street Cleared 10/5/2024 LIAM ODONOVAN
GPI Written Notices Cleared 10/30/2024 RAPHAEL ROSAS
Grading Pre-Inspection Cleared 10/30/2024 RAPHAEL ROSAS

Contact Information

Contractor Owner-Builder       ,
Engineer Telian,, Vartan; Lic. No.: C94330 11776 PIERCE ST      SYLMAR, CA 91342

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/11/2025 Partial Approval EVAN COOPER
ELECTRICAL-Rough 2/21/2025 Partial Approval ARAM AVEDISIAN
Footing/Foundation/Slab 2/21/2025 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 3/5/2025 Partial Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 3/24/2025 Partial Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 4/28/2025 Conditional Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 5/19/2025 Partial Approval ASHLEY THOMPSON
HVAC-Rough 5/19/2025 Corrections Issued ASHLEY THOMPSON
PLUMBING-Rough 5/19/2025 Approved ASHLEY THOMPSON
ELECTRICAL-Rough 6/3/2025 Corrections Issued BOBBY KEY
Shower Pan 6/3/2025 Corrections Issued BOBBY KEY
ELECTRICAL-Rough 6/5/2025 Approved ARAM AVEDISIAN
Shower Pan 6/9/2025 Approved DANIEL VERA
HVAC-Rough 6/12/2025 Approved ASHLEY THOMPSON
Interior/Exterior Lathing 6/12/2025 Partial Approval ASHLEY THOMPSON
Interior/Exterior Lathing 6/13/2025 Approved MEL KHACHATOURIAN
BUILDING-Rough-Frame 6/18/2025 Partial Approval TEMISTOCLES CAAL
Green Building Rough 6/18/2025 Approved TEMISTOCLES CAAL
BUILDING-Rough-Frame 6/30/2025 Approved STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 6/30/2025 Approved STEPHANIE SWANSON
Insulation 6/30/2025 Approved STEPHANIE SWANSON
Drywall Nailing 7/21/2025 Approved ASHLEY THOMPSON
PLUMBING-Final 10/10/2025 Approved ASHLEY THOMPSON
ELECTRICAL-Final 10/14/2025 Corrections Issued EVAN COOPER
HVAC-Final 10/14/2025 Corrections Issued EVAN COOPER
ELECTRICAL-Final 10/20/2025 Not Ready for Inspection ASHLEY THOMPSON
HVAC-Final 10/20/2025 Not Ready for Inspection ASHLEY THOMPSON
ELECTRICAL-Final 10/24/2025 Approved ASHLEY THOMPSON
HVAC-Final 10/24/2025 Approved ASHLEY THOMPSON
Final 10/29/2025 OK to Issue CofO MICHAEL ALLEN
Green Building Final 10/29/2025 Approved MICHAEL ALLEN
SGSOV-Seismic Gas S/O Valve 10/29/2025 SGSOV Approved MICHAEL ALLEN
Smoke Detectors 10/29/2025 Approved MICHAEL ALLEN