19410 W VANOWEN ST 91335
Certificate Information: 19410 W VANOWEN ST 91335
- Application / Permit
- 24014-20000-03508
- Plan Check / Job No.
- B24VN12432
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 16' X 17' ADDITION TO ENLARGE BEDROOM AND ADD BATHROOM. ALL WORK PER WFPP
- Permit Issued
- Issued on 9/11/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/7/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/8/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/16/2024 | JEROME MAGAT PALMA |
| Corrections Issued | 8/17/2024 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 9/4/2024 | APPLICANT |
| Issued | 9/11/2024 | APPLICANT |
| CofO in Progress | 4/14/2025 | ARUTYUN MADATYAN |
| Permit Finaled | 5/7/2025 | JOHN JANSON |
| CofO Issued | 5/7/2025 | JOHN JANSON |
| Permit Finaled | 5/7/2025 | JOHN JANSON |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 8/28/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 9/4/2024 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 11/5/2024 | Conditional Approval | ARUTYUN MADATYAN |
| Footing/Foundation/Slab | 11/6/2024 | Partial Approval | ARUTYUN MADATYAN |
| Footing/Foundation/Slab | 11/18/2024 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Rough | 11/18/2024 | Partial Approval | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/17/2024 | Partial Approval | ARUTYUN MADATYAN |
| Green Building Rough | 12/17/2024 | Not Ready for Inspection | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 1/8/2025 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Rough | 1/8/2025 | Approved | ARUTYUN MADATYAN |
| Green Building Rough | 1/8/2025 | Approved | ARUTYUN MADATYAN |
| HVAC-Rough | 1/8/2025 | Approved | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 1/8/2025 | Partial Approval | ARUTYUN MADATYAN |
| PLUMBING-Rough | 1/8/2025 | Approved | ARUTYUN MADATYAN |
| Insulation | 1/23/2025 | Approved | ARUTYUN MADATYAN |
| Shower Pan | 1/23/2025 | Approved | ARUTYUN MADATYAN |
| Drywall Nailing | 2/3/2025 | Approved | JUAN ALVARADO |
| Interior/Exterior Lathing | 2/3/2025 | Approved | JUAN ALVARADO |
| Final | 3/14/2025 | Corrections Issued | ARUTYUN MADATYAN |
| Green Building Final | 3/14/2025 | Approved | ARUTYUN MADATYAN |
| SGSOV-Seismic Gas S/O Valve | 3/14/2025 | SGSOV Approved | ARUTYUN MADATYAN |
| Smoke Detectors | 3/14/2025 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 3/27/2025 | Approved | ARUTYUN MADATYAN |
| Final | 3/27/2025 | Corrections Issued | ARUTYUN MADATYAN |
| HVAC-Final | 3/27/2025 | Approved | ARUTYUN MADATYAN |
| PLUMBING-Final | 3/27/2025 | Approved | ARUTYUN MADATYAN |
| Final | 4/14/2025 | OK to Issue CofO | ARUTYUN MADATYAN |