4953-4955 N CALVIN AVE 91326

Certificate Information: 4953-4955 N CALVIN AVE 91326

Application / Permit
24014-20000-03500
Plan Check / Job No.
B24VN12384
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Eplan Addition of 26' x 22' irregular shaped one story ADU per LAMC 12.22 A.33(c) and (e). All work done per engineer.
Permit Issued
Issued on 1/6/2025
Issuing Office
Current Status
Issued on 1/6/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/7/2024 APPLICANT
Assigned to Plan Check Engineer 8/15/2024 NAREG ATARIAN
Corrections Issued 8/18/2024 NAREG ATARIAN
Quality Review Completed 8/20/2024 OMID HEDAYAT
Applicant returned to address corrections 12/13/2024 NAREG ATARIAN
Plan Check Approved 1/2/2025 OMID HEDAYAT
Issued 1/6/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 8/22/2024 RYAN CASTRO
Roof/Waste drainage to street Cleared 8/22/2024 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 8/27/2024 RYAN CASTRO
Sewer availability Cleared 8/27/2024 RYAN CASTRO
Hydrant and Access approval Cleared 12/3/2024 GILBERT URREA
GPI Written Notices Cleared 12/13/2024 CHARLES POWELL
Grading Pre-Inspection Cleared 12/13/2024 CHARLES POWELL

Contact Information

Contractor Owner-Builder       ,
Engineer Braun,, Jason; Lic. No.: C70948 14390 SHAWNEE ST      MOORPARK, CA 93021

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/28/2025 Not Ready for Inspection JOHN KIDWELL
Footing/Foundation/Slab 1/28/2025 Not Ready for Inspection JOHN KIDWELL
Underground Mechanical 1/28/2025 Partial Approval JOHN KIDWELL
Deputy Drilled-In Anchors 1/31/2025 Partial Approval JOHN KIDWELL
Excavation/Setback/Form/Re-Bar 2/3/2025 Conditional Approval JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 2/13/2025 Partial Approval JOHN KIDWELL
BUILDING-Rough-Frame 2/28/2025 Not Ready for Inspection JOHN KIDWELL
ELECTRICAL-Rough 2/28/2025 Approved JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 2/28/2025 Partial Approval JOHN KIDWELL
Green Building Rough 2/28/2025 Approved JOHN KIDWELL
Interior/Exterior Lathing 2/28/2025 Partial Approval JOHN KIDWELL
PLUMBING-Rough 2/28/2025 Approved JOHN KIDWELL
Verify Sprinkler Sign Off 2/28/2025 Not Ready for Inspection JOHN KIDWELL
Wood Frame 2/28/2025 Partial Inspection JOHN KIDWELL
BUILDING-Rough-Frame 3/7/2025 Conditional Approval JOHN KIDWELL
HVAC-Rough 3/7/2025 Approved JOHN KIDWELL
Verify Sprinkler Sign Off 3/7/2025 Not Ready for Inspection JOHN KIDWELL
BUILDING-Rough-Frame 3/27/2025 Approved JOHN KIDWELL
Insulation 3/27/2025 Approved JOHN KIDWELL
Verify Sprinkler Sign Off 3/27/2025 Approved JOHN KIDWELL
ELECTRICAL-Final 5/29/2025 Approved JOHN KIDWELL
Final 5/29/2025 Not Ready for Inspection JOHN KIDWELL
Footing/Foundation/Slab 5/29/2025 Approved JOHN KIDWELL
Gas Test 5/29/2025 Approved JOHN KIDWELL
Green Building Final 5/29/2025 Not Ready for Inspection JOHN KIDWELL
HVAC-Final 5/29/2025 Not Ready for Inspection JOHN KIDWELL
PLUMBING-Final 5/29/2025 Not Ready for Inspection JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 5/29/2025 SGSOV Not Ready JOHN KIDWELL
Smoke Detectors 5/29/2025 Approved JOHN KIDWELL
Drywall Nailing 6/25/2025 Approved JOHN KIDWELL
Final 6/25/2025 Not Ready for Inspection JOHN KIDWELL
Green Building Final 6/25/2025 Approved JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 6/25/2025 SGSOV Approved JOHN KIDWELL