6322 E ELGIN ST 90042

Certificate Information: 6322 E ELGIN ST 90042

Application / Permit
24014-20000-03498
Plan Check / Job No.
B24VN12377
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
15'-8" X 10'-7" ADDITION TO AND CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 66323(a)(2)
Permit Issued
Issued on 3/13/2025
Issuing Office
Current Status
CofO Issued on 12/4/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/7/2024 APPLICANT
Assigned to Plan Check Engineer 8/14/2024 ARTIN ZARUKIAN
Corrections Issued 8/19/2024 ARTIN ZARUKIAN
Building Plans Picked Up 8/20/2024 APPLICANT
Applicant returned to address corrections 10/15/2024 MADISON ODELL
Applicant returned to address corrections 12/18/2024 JEROME MAGAT PALMA
Applicant returned to address corrections 2/18/2025 JEROME MAGAT PALMA
Plan Check Approved 3/13/2025 JEROME MAGAT PALMA
Issued 3/13/2025 APPLICANT
CofO in Progress 11/26/2025 DAVID WILLIAMS
No Progress 11/26/2025 CHARLES BOGHOSKHAN
CofO in Progress 11/26/2025 CHARLES BOGHOSKHAN
Permit Finaled 12/4/2025 DEROLD HAUFF
CofO Issued 12/4/2025 DEROLD HAUFF
Permit Finaled 12/4/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/22/2024 AMBER CAMPBELL
Roof/Waste drainage to street Cleared 8/22/2024 AMBER CAMPBELL
Roof/Waste drainage to street Cleared 10/3/2024 JUSTIN BICOL
Eng Process Fee Ord 176,300 Cleared 10/7/2024 JESSICA OPINION
Sewer availability Cleared 10/7/2024 JESSICA OPINION
Grading Pre-Inspection Cleared 10/7/2024 MICHAEL TEMPLE
Construction near power lines Cleared 12/18/2024 RIDWAN HARDY
HPOZ Cleared 2/19/2025 NATHALY DE LA PAZ

Contact Information

Contractor Regal Construction & Remodeling Inc; Lic. No.: 909023-B 19537 1/2 VENTURA BLVD      TARZANA, CA 91356
Engineer Standley,, Craig Erick; Lic. No.: C87675 60 VIA CARATAMA      SAN CLEMENTE, CA 92673

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/10/2025 Approved DAVID WILLIAMS
PLUMBING-Rough 5/6/2025 Partial Approval ALIZAH MAYAGOITIA
Deputy Drilled-In Anchors 5/8/2025 Conditional Approval DAVID WILLIAMS
Excavation/Setback/Form/Re-Bar 5/9/2025 Approved DAVID WILLIAMS
Footing/Foundation/Slab 5/14/2025 Approved DAVID WILLIAMS
Rough-Elec/Plmb/HVAC 7/8/2025 Corrections Issued DAVID WILLIAMS
Sewer 7/8/2025 Approved DAVID WILLIAMS
Rough-Elec/Plmb/HVAC 7/21/2025 Approved DAVID WILLIAMS
Wood Frame 7/21/2025 Approved DAVID WILLIAMS
Insulation 8/6/2025 Corrections Issued RONNIE MEDINA
Interior/Exterior Lathing 8/6/2025 Corrections Issued RONNIE MEDINA
Shower Pan 8/6/2025 Approved RONNIE MEDINA
Insulation 8/13/2025 Approved GEM DE OCAMPO
Interior/Exterior Lathing 8/13/2025 Partial Approval GEM DE OCAMPO
Drywall Nailing 8/19/2025 Approved DAVID WILLIAMS
Green Building Rough 8/19/2025 Approved DAVID WILLIAMS
Interior/Exterior Lathing 8/20/2025 Approved GEM DE OCAMPO
BUILDING-Rough-Frame 11/25/2025 Approved DAVID WILLIAMS
Final 11/25/2025 Corrections Issued DAVID WILLIAMS
Green Building Final 11/25/2025 Approved DAVID WILLIAMS
SGSOV-Seismic Gas S/O Valve 11/25/2025 SGSOV Approved DAVID WILLIAMS
Smoke Detectors 11/25/2025 Approved DAVID WILLIAMS
Final 11/26/2025 OK to Issue CofO DAVID WILLIAMS