- eplan: CONVERT 505 SF PORTION OF (E) SFD TO BE ATTACHED ADU. INTERIOR REMODEL OF (E) SFD
- Permit Issued
- Issued on 9/26/2024
- Issuing Office
- Current Status
- Issued on 9/26/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/6/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/9/2024 | JOSEPH RAFOLS |
| Corrections Issued | 8/9/2024 | JOSEPH RAFOLS |
| Plan Check Approved | 9/24/2024 | JOSEPH RAFOLS |
| Issued | 9/26/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 9/20/2024 | TREVOR QUAN |
| Sewer availability | Cleared | 9/20/2024 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 9/23/2024 | TREVOR QUAN |
Contact Information
| Architect | Kim,, Nam H; Lic. No.: C30825 | 1832 SANTA RENA DRIVE RANCHO PALOS VERDES, CA 90275 |
| Contractor | Owner-Builder | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/24/2025 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 4/8/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 4/8/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 4/8/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 5/7/2025 | Not Ready for Inspection | BRENDAN MORELLI |
| HVAC-Rough | 5/7/2025 | Not Ready for Inspection | BRENDAN MORELLI |
| PLUMBING-Rough | 5/7/2025 | Not Ready for Inspection | BRENDAN MORELLI |
| Special/Order Compliance | 5/7/2025 | Corrections Issued | BRENDAN MORELLI |
| Rough-Elec/Plmb/HVAC | 5/23/2025 | Corrections Issued | WAYNE REGESTER |
| ELECTRICAL-Rough | 7/31/2025 | No Access for Inspection | SABAS ALONSO |
| ELECTRICAL-Rough | 8/5/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 8/5/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 8/5/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Rough-Elec/Plmb/HVAC | 9/23/2025 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| Rough-Elec/Plmb/HVAC | 10/1/2025 | Partial Approval | JOHN QUINTANILLA |
| Rough-Elec/Plmb/HVAC | 10/3/2025 | Not Ready for Inspection | LUIS CASTRO |
| PLUMBING-Rough | 10/7/2025 | Approved | DANIEL GONZALEZ |
| Drywall Nailing | 10/10/2025 | Not Ready for Inspection | DANIEL GONZALEZ |
| ELECTRICAL-Rough | 10/10/2025 | Corrections Issued | DANIEL GONZALEZ |
| Insulation | 10/10/2025 | Approved | DANIEL GONZALEZ |
| Interior/Exterior Lathing | 10/10/2025 | Partial Approval | DANIEL GONZALEZ |
| Wood Frame | 10/10/2025 | Approved | DANIEL GONZALEZ |
| Drywall Nailing | 10/20/2025 | Approved | DANIEL GONZALEZ |
| ELECTRICAL-Rough | 10/20/2025 | Approved | DANIEL GONZALEZ |
| Interior/Exterior Lathing | 10/20/2025 | Approved | DANIEL GONZALEZ |
| BUILDING-Rough-Frame | 3/9/2026 | Conditional Approval | DANIEL GONZALEZ |
| Final | 3/9/2026 | Corrections Issued | DANIEL GONZALEZ |
| SGSOV-Seismic Gas S/O Valve | 3/9/2026 | SGSOV Approved | DANIEL GONZALEZ |
| Smoke Detectors | 3/9/2026 | Approved | DANIEL GONZALEZ |
| BUILDING-Rough-Frame | 3/10/2026 | Approved | DANIEL GONZALEZ |
| Final | 3/10/2026 | Conditional Approval | DANIEL GONZALEZ |