13151 1/2 W CARL ST 91331
Certificate Information: 13151 1/2 W CARL ST 91331
- Application / Permit
- 24014-20000-03455
- Plan Check / Job No.
- B24VN12076
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) TO (E) ATTACHED REC ROOM, AND (N) ATTACHED PATIO COVER PER LA STD PLAN P/BC 2023-006 AND WFPP.
- Permit Issued
- Issued on 9/4/2024
- Issuing Office
- Current Status
- CofO Issued on 4/22/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/6/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/9/2024 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 8/9/2024 | SEWADA ZADOORIAN MILAGARDI |
| Plan Check Approved | 9/1/2024 | SARKIS HARABEDIAN |
| Issued | 9/4/2024 | APPLICANT |
| CofO in Progress | 4/8/2025 | MICHEL ABAJAN |
| Permit Finaled | 4/22/2025 | RUBEN SALAS |
| CofO Issued | 4/22/2025 | RUBEN SALAS |
| Permit Finaled | 4/22/2025 | RUBEN SALAS |
Permit Application Clearance Information
| ZI | Cleared | 8/12/2024 | NATHAN ROMINE |
| ZI | Cleared | 8/12/2024 | NATHAN ROMINE |
| Address approval | Cleared | 8/13/2024 | KEVIN CHUNG |
| Roof/Waste drainage to street | Cleared | 8/13/2024 | KEVIN CHUNG |
| Eng Process Fee Ord 176,300 | Cleared | 8/16/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 8/16/2024 | EDGAR ALCARAZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/9/2024 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 10/10/2024 | Approved | MICHEL ABAJAN |
| METHANE-Barrier | 10/10/2024 | Approved | MICHEL ABAJAN |
| METHANE-Subgrade | 10/10/2024 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 10/15/2024 | Corrections Issued | ROBERT GOLD |
| Sewer | 10/15/2024 | Approved | ROBERT GOLD |
| PLUMBING-Rough | 10/18/2024 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 11/12/2024 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 11/12/2024 | Approved | MICHEL ABAJAN |
| Green Building Rough | 11/12/2024 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 11/12/2024 | Approved | MICHEL ABAJAN |
| METHANE-Rough | 11/12/2024 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 11/12/2024 | Approved | MICHEL ABAJAN |
| Insulation | 11/15/2024 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 11/15/2024 | Approved | KEVIN BERBERYAN |
| Drywall Nailing | 11/21/2024 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 3/25/2025 | Approved | MICHEL ABAJAN |
| Final | 3/25/2025 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 3/25/2025 | Approved | MICHEL ABAJAN |
| HVAC-Final | 3/25/2025 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 3/25/2025 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 3/25/2025 | SGSOV Approved | MICHEL ABAJAN |
| Smoke Detectors | 3/25/2025 | Approved | MICHEL ABAJAN |
| Final | 4/7/2025 | OK to Issue CofO | MICHEL ABAJAN |