12610 N AMBOY AVE 91342
Certificate Information: 12610 N AMBOY AVE 91342
- Application / Permit
- 24014-20000-03454
- Plan Check / Job No.
- B24VN12009
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Eplan: NEW 20' x 18'6" IRREGULAR SHAPED ADDITION ( 388 S.F. ) WITH ENCLOSING A PORTION OF ATTACHED PATIO COVER (47 SF) TO SINGLE FAMILY.
- Permit Issued
- Issued on 12/26/2024
- Issuing Office
- Current Status
- CofO Issued on 5/28/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/7/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/9/2024 | MIROOSH KHACHATOORIAN |
| Corrections Issued | 8/9/2024 | MIROOSH KHACHATOORIAN |
| Applicant returned to address corrections | 8/15/2024 | MIROOSH KHACHATOORIAN |
| Applicant returned to address corrections | 8/21/2024 | MIROOSH KHACHATOORIAN |
| Plan Check Approved | 8/26/2024 | MIROOSH KHACHATOORIAN |
| Issued | 12/26/2024 | APPLICANT |
| CofO in Progress | 3/13/2026 | KEVIN BERBERYAN |
| Permit Finaled | 5/28/2026 | RUBEN SALAS |
| Permit Finaled | 5/28/2026 | RUBEN SALAS |
| CofO Issued | 5/28/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 8/12/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 8/13/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 8/13/2024 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/13/2025 | Partial Inspection | KEVIN BERBERYAN |
| Underground Mechanical | 1/22/2025 | Approved | KEVIN BERBERYAN |
| Excavation/Setback/Form/Re-Bar | 1/29/2025 | Approved | KEVIN BERBERYAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/6/2025 | Partial Approval | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 4/7/2025 | Conditional Approval | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 4/7/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 4/10/2025 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 4/10/2025 | Approved | KEVIN BERBERYAN |
| PLUMBING-Rough | 4/10/2025 | Approved | KEVIN BERBERYAN |
| Insulation | 4/29/2025 | Approved | KEVIN BERBERYAN |
| Shower Pan | 4/29/2025 | Approved | KEVIN BERBERYAN |
| Drywall Nailing | 5/5/2025 | Approved | KEVIN BERBERYAN |
| Green Building Rough | 5/5/2025 | Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 10/6/2025 | Approved | KEVIN BERBERYAN |
| Final | 10/6/2025 | Corrections Issued | KEVIN BERBERYAN |
| Footing/Foundation/Slab | 10/6/2025 | Approved | KEVIN BERBERYAN |
| Green Building Final | 10/6/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 10/6/2025 | SGSOV Approved | KEVIN BERBERYAN |
| Smoke Detectors | 10/6/2025 | Approved | KEVIN BERBERYAN |
| Final | 3/13/2026 | OK to Issue CofO | KEVIN BERBERYAN |