12661 W WELBY WAY 91606

Certificate Information: 12661 W WELBY WAY 91606

Application / Permit
24014-20000-03435
Plan Check / Job No.
B24VN11874
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 15' x 13'ADDITION TO AND CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). WORK DONE PER ENGINEER DESIGN.
Permit Issued
Issued on 9/13/2024
Issuing Office
Valley
Current Status
Issued on 9/13/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 8/2/2024 APPLICANT
Assigned to Plan Check Engineer 8/9/2024 ARTIN ZARUKIAN
Corrections Issued 8/10/2024 ARTIN ZARUKIAN
Building Plans Picked Up 8/15/2024 APPLICANT
Applicant returned to address corrections 9/10/2024 ISIS ARGUETA
Plan Check Approved 9/11/2024 MIROOSH KHACHATOORIAN
Issued 9/13/2024 APPLICANT

Permit Application Clearance Information

Construction near power lines Cleared 8/30/2024 OSCAR CASTRO
Address approval Cleared 9/3/2024 KEVIN CHUNG
Roof/Waste drainage to street Cleared 9/3/2024 KEVIN CHUNG
Sewer availability Cleared 9/4/2024 KEVIN CHUNG
Eng Process Fee Ord 176,300 Cleared 9/11/2024 RYAN CASTRO

Contact Information

Contractor Dream Home Remodeling Inc; Lic. No.: 792977-B 22311 VENTURA BLVD SUITE 110      WOODLAND HILLS, CA 91364
Engineer Mayorga,, Jose Aguinaldo; Lic. No.: C50322 20457 OREY PL      WINNETKA, CA 91306

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/27/2024 Corrections Issued OGANES TARAKHCHYAN
PLUMBING-Rough 9/27/2024 Partial Approval OGANES TARAKHCHYAN
Footing/Foundation/Slab 10/2/2024 Partial Approval GAREN HAYRAPETYAN
PLUMBING-Rough 10/2/2024 Partial Approval GAREN HAYRAPETYAN
Deputy Drilled-In Anchors 10/3/2024 Conditional Approval JUAN VALENZUELA
Deputy Drilled-In Anchors 10/31/2024 Conditional Approval RAUL OLAGI
ELECTRICAL-Rough 11/1/2024 Approved OGANES TARAKHCHYAN
Green Building Rough 11/1/2024 Not Ready for Inspection OGANES TARAKHCHYAN
PLUMBING-Rough 11/1/2024 Approved OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 11/14/2024 Approved OGANES TARAKHCHYAN
HVAC-Rough 11/14/2024 Corrections Issued OGANES TARAKHCHYAN
Wood Frame 11/14/2024 Partial Approval OGANES TARAKHCHYAN
Shower Pan 11/26/2024 Corrections Issued OGANES TARAKHCHYAN
BUILDING-Rough-Frame 12/3/2024 Approved OGANES TARAKHCHYAN
Green Building Rough 12/3/2024 Approved OGANES TARAKHCHYAN
HVAC-Rough 12/3/2024 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 12/3/2024 Partial Approval OGANES TARAKHCHYAN
Shower Pan 12/3/2024 Approved OGANES TARAKHCHYAN
Insulation 12/6/2024 Approved GAREN HAYRAPETYAN
Wood Frame 12/6/2024 Approved GAREN HAYRAPETYAN
Drywall Nailing 12/9/2024 Not Ready for Inspection GAREN HAYRAPETYAN
Insulation 12/9/2024 Approved GAREN HAYRAPETYAN
Drywall Nailing 12/13/2024 Approved OGANES TARAKHCHYAN
Pre-Inspection 12/13/2024 Approved OGANES TARAKHCHYAN
Pre-Inspection 1/2/2025 Approved MICHAEL CORTEZ
Final 4/2/2025 Corrections Issued GAREN HAYRAPETYAN
Footing/Foundation/Slab 4/2/2025 Approved GAREN HAYRAPETYAN
Green Building Final 4/2/2025 Not Ready for Inspection GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 4/2/2025 SGSOV No Gas GAREN HAYRAPETYAN
Smoke Detectors 4/2/2025 Approved GAREN HAYRAPETYAN
Final 4/9/2025 Not Ready for Inspection OGANES TARAKHCHYAN
Green Building Final 4/9/2025 Approved OGANES TARAKHCHYAN
ELECTRICAL-Final 8/8/2025 Approved GAREN HAYRAPETYAN
Final 8/8/2025 Corrections Issued GAREN HAYRAPETYAN
HVAC-Final 8/8/2025 Approved GAREN HAYRAPETYAN
PLUMBING-Final 8/8/2025 Approved GAREN HAYRAPETYAN
Service/Power Release 8/8/2025 Approved GAREN HAYRAPETYAN
Final 12/15/2025 Not Ready for Inspection WAYNE REGESTER