7306 N FARMDALE AVE 91605
Certificate Information: 7306 N FARMDALE AVE 91605
- Application / Permit
- 24014-20000-03429
- Plan Check / Job No.
- B24VN11838
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: ADDITION (300 SF) AT THE REAR TO AN (E) SFD AND 198 SF NEW PATIO DECK AT THE REAR.
- Permit Issued
- Issued on 9/4/2024
- Issuing Office
- Current Status
- CofO Issued on 2/27/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/2/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/8/2024 | LUKE GONZALES |
| Corrections Issued | 8/9/2024 | LUKE GONZALES |
| Applicant returned to address corrections | 8/28/2024 | SUNMIN LEE |
| Applicant returned to address corrections | 8/29/2024 | TSE MING HUANG |
| Plan Check Approved | 9/3/2024 | NEHEMIAS RAMOS |
| Issued | 9/4/2024 | APPLICANT |
| CofO in Progress | 1/31/2025 | ROBERTO PALACIOS-LOPEZ |
| Permit Finaled | 2/27/2025 | RUBEN SALAS |
| CofO Issued | 2/27/2025 | RUBEN SALAS |
| Permit Finaled | 2/27/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 8/19/2024 | CARLOS RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/21/2024 | CARLOS RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/23/2024 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 9/24/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 10/16/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Wood Frame | 10/16/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Deputy Wood Construction | 10/24/2024 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 10/25/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 10/25/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Wood Frame | 10/25/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 10/29/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 11/1/2024 | Approved | JOSE AVILA |
| Insulation | 11/1/2024 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 11/1/2024 | Approved | JOSE AVILA |
| Wood Frame | 11/1/2024 | Approved | JOSE AVILA |
| Drywall Nailing | 11/6/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 11/12/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 11/15/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Drywall Nailing | 12/26/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 12/26/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 12/26/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 12/26/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 12/26/2024 | SGSOV Approved | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 12/26/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 1/10/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Final | 1/10/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 1/22/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Pre-Inspection | 1/28/2025 | Partial Inspection | JUAN VALENZUELA |
| Final | 1/31/2025 | OK to Issue CofO | ROBERTO PALACIOS-LOPEZ |