18406 W JOVAN ST 91335

Certificate Information: 18406 W JOVAN ST 91335

Application / Permit
24014-20000-03428
Plan Check / Job No.
B24VN11823
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
addition at front and rear to existing 1 story single family dewlling per engineer design
Permit Issued
Issued on 9/10/2024
Issuing Office
Current Status
CofO Issued on 7/21/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/5/2024 APPLICANT
Assigned to Plan Check Engineer 8/8/2024 DANIEL SANJUAN
Corrections Issued 8/9/2024 DANIEL SANJUAN
Applicant returned to address corrections 8/28/2024 AUNG SOE
Plan Check Approved 9/4/2024 JOSEPH RAFOLS
Issued 9/10/2024 APPLICANT
CofO in Progress 6/27/2025 MORRIS JACKSON
CofO Issued 7/21/2025 DANIEL ORRANTE
Permit Finaled 7/21/2025 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/12/2024 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 8/12/2024 BIAINA HARITUNIAN
Sewer availability Cleared 8/12/2024 BIAINA HARITUNIAN

Contact Information

Contractor Portico Construction Inc; Lic. No.: 1065485-B       ,
Engineer Baluyut,, Agustin Pangilinan; Lic. No.: C66025 22828 S CYPRESS DR      CARSON, CA 90745

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/11/2024 Partial Approval JON MCHUGH
Deputy Drilled-In Anchors 10/23/2024 Conditional Approval MORRIS JACKSON
Excavation/Setback/Form/Re-Bar 12/4/2024 Approved MORRIS JACKSON
Special/Order Compliance 12/4/2024 Corrections Issued MORRIS JACKSON
BUILDING-Rough-Frame 12/26/2024 Corrections Issued JOHN COLEMAN
Green Building Rough 12/26/2024 Not Ready for Inspection JOHN COLEMAN
Deputy Steel/Welding 1/6/2025 Conditional Approval JON MCHUGH
Insulation 1/7/2025 Partial Approval MORRIS JACKSON
Deputy Drilled-In Anchors 1/8/2025 Conditional Approval MORRIS JACKSON
Excavation/Setback/Form/Re-Bar 1/9/2025 Corrections Issued MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 1/9/2025 Partial Approval MORRIS JACKSON
Deputy Other (see comments) 1/13/2025 Conditional Approval MORRIS JACKSON
Footing/Foundation/Slab 1/13/2025 Approved MORRIS JACKSON
Structural Steel Frame 1/13/2025 Approved MORRIS JACKSON
PLUMBING-Rough 1/17/2025 Approved MORRIS JACKSON
ELECTRICAL-Rough 2/28/2025 Approved MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 2/28/2025 Partial Approval MORRIS JACKSON
Green Building Rough 2/28/2025 Not Ready for Inspection MORRIS JACKSON
HVAC-Rough 2/28/2025 Corrections Issued MORRIS JACKSON
Wood Frame 2/28/2025 Not Ready for Inspection MORRIS JACKSON
Deputy Wood Construction 3/4/2025 Conditional Approval MORRIS JACKSON
BUILDING-Rough-Frame 3/21/2025 Approved MORRIS JACKSON
Gas Test 3/21/2025 Not Ready for Inspection MORRIS JACKSON
Green Building Rough 3/21/2025 Approved MORRIS JACKSON
HVAC-Rough 3/21/2025 Approved MORRIS JACKSON
Interior/Exterior Lathing 3/21/2025 Partial Approval MORRIS JACKSON
SGSOV-Seismic Gas S/O Valve 3/21/2025 SGSOV Not Ready MORRIS JACKSON
Wood Frame 3/21/2025 Approved MORRIS JACKSON
Gas Test 3/28/2025 Approved MORRIS JACKSON
Insulation 3/28/2025 Approved MORRIS JACKSON
Shower Pan 4/4/2025 Approved MORRIS JACKSON
Drywall Nailing 4/11/2025 Approved HENRY KIM
Interior/Exterior Lathing 4/11/2025 Partial Approval HENRY KIM
Interior/Exterior Lathing 4/22/2025 Approved MORRIS JACKSON
Green Building Final 6/13/2025 Approved MORRIS JACKSON
SGSOV-Seismic Gas S/O Valve 6/13/2025 SGSOV Approved MORRIS JACKSON
Smoke Detectors 6/13/2025 Approved MORRIS JACKSON
ELECTRICAL-Final 6/27/2025 Approved MORRIS JACKSON
Final 6/27/2025 OK to Issue CofO MORRIS JACKSON
HVAC-Final 6/27/2025 Approved MORRIS JACKSON
PLUMBING-Final 6/27/2025 Approved MORRIS JACKSON