6015-6017 W 76TH PL 90045

Certificate Information: 6015-6017 W 76TH PL 90045

Application / Permit
24014-20000-03419
Plan Check / Job No.
B24VN11682
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) 20' x 18' GARAGE WITH 10' x 17'-6" ADDITION TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e) SEE COMMENTS
Permit Issued
Issued on 9/5/2024
Issuing Office
Valley
Current Status
CofO Issued on 12/12/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/1/2024 APPLICANT
Assigned to Plan Check Engineer 8/7/2024 MOHAMMAD ESMAILI
Corrections Issued 8/8/2024 MOHAMMAD ESMAILI
Building Plans Picked Up 8/12/2024 APPLICANT
Plan Check Approved 9/5/2024 SEWADA ZADOORAN MILAGARDI
Issued 9/5/2024 APPLICANT
CofO in Progress 12/8/2025 JESUS PINEDA
Permit Finaled 12/12/2025 RICHARD STEINBACH
CofO Issued 12/12/2025 RICHARD STEINBACH
Permit Finaled 12/12/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 8/19/2024 DIANA RENTERIA
Grading Pre-Inspection Cleared 8/19/2024 CHARLES POWELL
Roof/Waste drainage to street Cleared 8/19/2024 DIANA RENTERIA
Specific Plan Cleared 8/28/2024 PEDRO AYALA
Eng Process Fee Ord 176,300 Cleared 8/30/2024 DINAH GARIN
Sewer availability Cleared 8/30/2024 DINAH GARIN

Contact Information

Contractor David'S Crew Inc; Lic. No.: 902629-B 1320 KELLAM AVE      LOS ANGELES, CA 90026
Engineer Morales,, Carlos Alberto; Lic. No.: C69972 38100 SAN MATEO AVE      PALMDALE, CA 93551

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/11/2024 Partial Approval BOBBY KEY
Underground Mechanical 10/11/2024 Partial Approval BOBBY KEY
Footing/Foundation/Slab 10/23/2024 Not Ready for Inspection BOBBY KEY
Excavation/Setback/Form/Re-Bar 10/25/2024 Not Ready for Inspection JESUS PINEDA
Footing/Foundation/Slab 10/25/2024 Corrections Issued JESUS PINEDA
BUILDING-Rough-Frame 2/28/2025 Not Ready for Inspection TEMISTOCLES CAAL
ELECTRICAL-Rough 2/28/2025 Partial Approval TEMISTOCLES CAAL
Footing/Foundation/Slab 2/28/2025 Approved TEMISTOCLES CAAL
Green Building Rough 2/28/2025 Not Ready for Inspection TEMISTOCLES CAAL
HVAC-Rough 2/28/2025 Corrections Issued TEMISTOCLES CAAL
PLUMBING-Rough 2/28/2025 Approved TEMISTOCLES CAAL
ELECTRICAL-Rough 4/1/2025 Corrections Issued JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 4/1/2025 Partial Approval JESUS PINEDA
Green Building Rough 4/1/2025 Not Ready for Inspection JESUS PINEDA
HVAC-Rough 4/1/2025 Approved JESUS PINEDA
Interior/Exterior Lathing 4/7/2025 Partial Approval TEMISTOCLES CAAL
BUILDING-Rough-Frame 4/10/2025 Approved JESUS PINEDA
ELECTRICAL-Rough 4/10/2025 Approved JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 4/10/2025 Approved JESUS PINEDA
Green Building Rough 4/10/2025 Approved JESUS PINEDA
Shower Pan 4/10/2025 Approved JESUS PINEDA
Insulation 4/11/2025 Approved JAYLIN GRAVITTE
Interior/Exterior Lathing 4/11/2025 Approved JAYLIN GRAVITTE
Drywall Nailing 4/17/2025 Approved BOBBY KEY
ELECTRICAL-Final 4/17/2025 Corrections Issued BOBBY KEY
Final 11/7/2025 Corrections Issued JESUS PINEDA
Green Building Final 11/7/2025 Corrections Issued JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 11/7/2025 SGSOV Approved JESUS PINEDA
Smoke Detectors 11/7/2025 Approved JESUS PINEDA
Final 11/14/2025 Not Ready for Inspection JESUS PINEDA
Green Building Final 11/14/2025 Not Ready for Inspection JESUS PINEDA
Final 12/2/2025 OK to Issue CofO JESUS PINEDA
Green Building Final 12/2/2025 Approved JESUS PINEDA