8061 N RHODES AVE 91605
Certificate Information: 8061 N RHODES AVE 91605
- Application / Permit
- 24014-20000-03383
- Plan Check / Job No.
- B24VN11397
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD 8'-3" x 21'-5" LAUNDRY AND STORAGE ROOM TO REAR OF (E) SFD. ALL WORK PER WFPP
- Permit Issued
- Issued on 8/9/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/31/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/30/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/30/2024 | ANGELICA DAVE |
| Corrections Issued | 7/30/2024 | ANGELICA DAVE |
| Applicant returned to address corrections | 8/7/2024 | ARAMIK SHAHMIRZAIAN |
| Issued | 8/9/2024 | APPLICANT |
| CofO in Progress | 7/24/2025 | MATTHEW NELSON |
| Permit Finaled | 7/31/2025 | RUBEN SALAS |
| CofO Issued | 7/31/2025 | RUBEN SALAS |
| Permit Finaled | 7/31/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/1/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 8/1/2024 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| WILLIAM WREN, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/23/2024 | Corrections Issued | MATTHEW NELSON |
| Footing/Foundation/Slab | 1/7/2025 | Partial Approval | MATTHEW NELSON |
| Excavation/Setback/Form/Re-Bar | 1/21/2025 | Not Ready for Inspection | MATTHEW NELSON |
| Grounding or Bonding | 1/21/2025 | Not Ready for Inspection | MATTHEW NELSON |
| Wood Frame | 1/21/2025 | Not Ready for Inspection | MATTHEW NELSON |
| Deputy Drilled-In Anchors | 1/22/2025 | Conditional Approval | MATTHEW NELSON |
| Excavation/Setback/Form/Re-Bar | 1/23/2025 | Approved | MATTHEW NELSON |
| Footing/Foundation/Slab | 1/23/2025 | Approved | MATTHEW NELSON |
| Rough-Elec/Plmb/HVAC | 3/12/2025 | Corrections Issued | MATTHEW NELSON |
| Wood Frame | 3/12/2025 | Corrections Issued | MATTHEW NELSON |
| ELECTRICAL-Rough | 4/3/2025 | Approved | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/3/2025 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 4/3/2025 | Approved | MATTHEW NELSON |
| Sewer | 4/3/2025 | Not Ready for Inspection | MATTHEW NELSON |
| Insulation | 4/21/2025 | Partial Approval | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 4/21/2025 | Partial Approval | MICHAEL CORTEZ |
| Insulation | 5/7/2025 | Approved | JOAQUIN GREENOUGH |
| Drywall Nailing | 5/12/2025 | Approved | NICHOLAS TROWBRIDGE |
| Green Building Rough | 5/12/2025 | Approved | NICHOLAS TROWBRIDGE |
| BUILDING-Rough-Frame | 7/16/2025 | Approved | MATTHEW NELSON |
| Final | 7/16/2025 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 7/16/2025 | Approved | MATTHEW NELSON |
| Smoke Detectors | 7/16/2025 | Approved | MATTHEW NELSON |
| Final | 7/18/2025 | Partial Approval | MATTHEW NELSON |
| Final | 7/24/2025 | OK to Issue CofO | MATTHEW NELSON |