160-160 1/4 W 59TH ST 90003

Certificate Information: 160-160 1/4 W 59TH ST 90003

Application / Permit
24014-20000-03372
Plan Check / Job No.
B24VN11337
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERSION OF EXISTING ATTACHED GARAGE AND STORAGE WITH ADDITION INTO ATTACHED ACCESSORY DWELLING UNIT PER LAMC12.22A.33(c) and(e)
Permit Issued
Issued on 2/3/2025
Issuing Office
Current Status
CofO Issued on 5/28/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/30/2024 APPLICANT
Assigned to Plan Check Engineer 8/2/2024 LAWRENCE QUIRANTE
Corrections Issued 8/4/2024 LAWRENCE QUIRANTE
Applicant returned to address corrections 9/4/2024 LAWRENCE QUIRANTE
Applicant returned to address corrections 10/16/2024 LAWRENCE QUIRANTE
Applicant returned to address corrections 12/28/2024 CARLOS MONTES
Plan Check Approved 2/1/2025 CARLOS MONTES
Issued 2/3/2025 APPLICANT
CofO in Progress 5/23/2026 ALEJANDRO DE ARTOLA
CofO in Progress 5/23/2026 ALEJANDRO DE ARTOLA
CofO in Progress 5/26/2026 ALEJANDRO DE ARTOLA
Permit Finaled 5/28/2026 DEROLD HAUFF
CofO Issued 5/28/2026 DEROLD HAUFF
Permit Finaled 5/28/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/13/2024 TREVOR QUAN
Roof/Waste drainage to street Cleared 8/13/2024 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 8/14/2024 TREVOR QUAN
Sewer availability Cleared 8/14/2024 TREVOR QUAN

Contact Information

Contractor Owner-Builder       ,
Engineer Sivushenka,, Mikita; Lic. No.: C87698 22814 DOLOROSA ST      WOODLAND HILLS, CA 91367

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 6/20/2025 Corrections Issued WAYNE REGESTER
Final 6/20/2025 Corrections Issued WAYNE REGESTER
Footing/Foundation/Slab 6/20/2025 Corrections Issued WAYNE REGESTER
Green Building Final 6/20/2025 Corrections Issued WAYNE REGESTER
Green Building Rough 6/20/2025 Corrections Issued WAYNE REGESTER
SGSOV-Seismic Gas S/O Valve 6/20/2025 SGSOV Not Ready WAYNE REGESTER
Smoke Detectors 6/20/2025 Corrections Issued WAYNE REGESTER
BUILDING-Rough-Frame 8/4/2025 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 8/4/2025 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 8/4/2025 Corrections Issued ALEJANDRO DE ARTOLA
Pre-Inspection 8/4/2025 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 8/12/2025 Corrections Issued ALEJANDRO DE ARTOLA
Pre-Inspection 8/12/2025 Corrections Issued ALEJANDRO DE ARTOLA
Pre-Inspection 8/21/2025 Partial Approval ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 9/8/2025 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 9/22/2025 Corrections Issued ALEJANDRO DE ARTOLA
Underground Mechanical 9/22/2025 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 9/23/2025 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 9/23/2025 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 10/22/2025 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 10/22/2025 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 10/22/2025 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 10/22/2025 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 11/3/2025 Approved LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 11/3/2025 Corrections Issued LUIS CASTRO
HVAC-Rough 11/3/2025 Corrections Issued LUIS CASTRO
PLUMBING-Rough 11/3/2025 Partial Approval LUIS CASTRO
BUILDING-Rough-Frame 11/18/2025 Corrections Issued LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 11/18/2025 Approved LUIS CASTRO
Green Building Rough 11/18/2025 Not Ready for Inspection LUIS CASTRO
HVAC-Rough 11/18/2025 Approved LUIS CASTRO
PLUMBING-Rough 11/18/2025 Approved LUIS CASTRO
Insulation 12/2/2025 Approved ANTHONY RAMOS
Deputy Wood Construction 12/9/2025 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 12/9/2025 Partial Approval ALEJANDRO DE ARTOLA
Green Building Rough 12/9/2025 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 12/9/2025 Partial Approval ALEJANDRO DE ARTOLA
Drywall Nailing 12/19/2025 Approved ALEX COLIN
Interior/Exterior Lathing 1/16/2026 Approved ALEJANDRO DE ARTOLA
Shower Pan 1/16/2026 Approved ALEJANDRO DE ARTOLA
Pre-Inspection 2/6/2026 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 3/9/2026 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 3/31/2026 Approved ALEJANDRO DE ARTOLA
Final 3/31/2026 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 3/31/2026 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 3/31/2026 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 3/31/2026 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 3/31/2026 SGSOV Not Required ALEJANDRO DE ARTOLA
ELECTRICAL-Final 5/21/2026 Approved ALEJANDRO DE ARTOLA
HVAC-Final 5/21/2026 Approved ALEJANDRO DE ARTOLA
Final 5/22/2026 OK to Issue CofO ALEJANDRO DE ARTOLA
Green Building Final 5/22/2026 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 5/22/2026 Approved ALEJANDRO DE ARTOLA
Smoke Detectors 5/22/2026 Approved ALEJANDRO DE ARTOLA