9829 N STANWIN AVE 91331

Certificate Information: 9829 N STANWIN AVE 91331

Application / Permit
24014-20000-03341
Plan Check / Job No.
B24VN11169
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD TO & REMNODEL SFD
Permit Issued
Issued on 8/19/2024
Issuing Office
Current Status
CofO Issued on 4/25/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/29/2024 APPLICANT
Assigned to Plan Check Engineer 8/1/2024 JESSE ARELLANO
Corrections Issued 8/2/2024 JESSE ARELLANO
Building Plans Picked Up 8/9/2024 APPLICANT
Plan Check Approved 8/19/2024 MOHAMMAD ESMAILI
Issued 8/19/2024 APPLICANT
CofO in Progress 12/17/2024 MICHEL ABAJAN
Permit Finaled 4/25/2025 RUBEN SALAS
CofO Issued 4/25/2025 RUBEN SALAS
Permit Finaled 4/25/2025 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 8/8/2024 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 8/9/2024 RYAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Andrejic,, Milos; Lic. No.: C67443 3601 BEVERLY RIDGE DR      SHERMAN OAKS, CA 91423

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/9/2024 Partial Inspection MICHEL ABAJAN
Deputy Drilled-In Anchors 9/12/2024 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 9/12/2024 Approved MICHEL ABAJAN
METHANE-Barrier 9/12/2024 Approved MICHEL ABAJAN
METHANE-Subgrade 9/12/2024 Approved MICHEL ABAJAN
PLUMBING-Rough 9/16/2024 Partial Approval MICHEL ABAJAN
Pre-Inspection 9/16/2024 Partial Approval MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 9/25/2024 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 9/27/2024 Approved MICHEL ABAJAN
ELECTRICAL-Rough 9/27/2024 Approved MICHEL ABAJAN
Green Building Rough 9/27/2024 Approved MICHEL ABAJAN
HVAC-Rough 9/27/2024 Approved MICHEL ABAJAN
METHANE-Rough 9/27/2024 Approved MICHEL ABAJAN
PLUMBING-Rough 9/27/2024 Approved MICHEL ABAJAN
Insulation 9/30/2024 Approved MICHEL ABAJAN
Drywall Nailing 10/1/2024 Approved MICHEL ABAJAN
ELECTRICAL-Final 12/16/2024 Approved MICHEL ABAJAN
Final 12/16/2024 OK to Issue CofO MICHEL ABAJAN
Green Building Final 12/16/2024 Approved MICHEL ABAJAN
HVAC-Final 12/16/2024 Approved MICHEL ABAJAN
PLUMBING-Final 12/16/2024 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 12/16/2024 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 12/16/2024 Approved MICHEL ABAJAN