6020 N ALLOTT AVE 91401
Certificate Information: 6020 N ALLOTT AVE 91401
- Application / Permit
- 24014-20000-03328
- Plan Check / Job No.
- B24VN11103
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan. Extend (e) front entry porch and interior / exterior remodel to (e) SFD
- Permit Issued
- Issued on 9/21/2024
- Issuing Office
- Current Status
- Issued on 9/21/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/29/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/1/2024 | YASHAR EMAMI |
| Corrections Issued | 8/2/2024 | YASHAR EMAMI |
| Applicant returned to address corrections | 8/26/2024 | YASHAR EMAMI |
| Applicant returned to address corrections | 9/3/2024 | AMY GUEVARRA |
| Plan Check Approved | 9/15/2024 | REZA HAGHIGHAT |
| Issued | 9/21/2024 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/28/2024 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 8/28/2024 | CARLOS AGUILERA |
Contact Information
| Architect | Herrera,, David; Lic. No.: NA35011 | , |
| Contractor | Owner-Builder | , |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/25/2025 | Approved | GAREN HAYRAPETYAN |
| PLUMBING-Rough | 7/16/2025 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 7/18/2025 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Drilled-In Anchors | 7/22/2025 | Conditional Approval | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 7/23/2025 | Partial Approval | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 7/23/2025 | Partial Approval | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/3/2025 | Partial Approval | WAYNE REGESTER |
| Wood Frame | 9/3/2025 | Partial Approval | WAYNE REGESTER |
| BUILDING-Rough-Frame | 9/9/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 9/9/2025 | Approved | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/9/2025 | Approved | OGANES TARAKHCHYAN |
| Green Building Rough | 9/9/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| HVAC-Rough | 9/9/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 9/9/2025 | Partial Approval | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 9/9/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Wood Frame | 9/9/2025 | Partial Approval | OGANES TARAKHCHYAN |
| HVAC-Rough | 9/11/2025 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 9/11/2025 | Approved | OGANES TARAKHCHYAN |
| Wood Frame | 9/11/2025 | Approved | OGANES TARAKHCHYAN |
| Insulation | 9/22/2025 | Approved | WAYNE REGESTER |
| Drywall Nailing | 10/8/2025 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 11/14/2025 | Approved | WAYNE REGESTER |
| Shower Pan | 11/14/2025 | Approved | WAYNE REGESTER |
| BUILDING-Rough-Frame | 1/7/2026 | Approved | WAYNE REGESTER |
| Final | 1/7/2026 | Not Ready for Inspection | WAYNE REGESTER |
| Green Building Final | 1/7/2026 | Not Ready for Inspection | WAYNE REGESTER |
| Green Building Rough | 1/7/2026 | Approved | WAYNE REGESTER |
| SGSOV-Seismic Gas S/O Valve | 1/7/2026 | SGSOV Not Ready | WAYNE REGESTER |
| Smoke Detectors | 1/7/2026 | Order to Comply Issued | WAYNE REGESTER |
| Final | 1/9/2026 | Not Ready for Inspection | WAYNE REGESTER |
| Green Building Final | 1/9/2026 | Not Ready for Inspection | WAYNE REGESTER |
| SGSOV-Seismic Gas S/O Valve | 1/9/2026 | SGSOV Not Ready | WAYNE REGESTER |
| Smoke Detectors | 1/9/2026 | Not Ready for Inspection | WAYNE REGESTER |
| ELECTRICAL-Final | 1/23/2026 | Approved | WAYNE REGESTER |
| HVAC-Final | 1/23/2026 | Approved | WAYNE REGESTER |
| PLUMBING-Final | 1/23/2026 | Approved | WAYNE REGESTER |
| Final | 1/27/2026 | Not Ready for Inspection | WAYNE REGESTER |
| Green Building Final | 1/27/2026 | Approved | WAYNE REGESTER |
| SGSOV-Seismic Gas S/O Valve | 1/27/2026 | SGSOV Approved | WAYNE REGESTER |
| Smoke Detectors | 1/27/2026 | Approved | WAYNE REGESTER |
| Final | 5/27/2026 | Corrections Issued | WAYNE REGESTER |