10653 N HELENDALE AVE 91042
Certificate Information: 10653 N HELENDALE AVE 91042
- Application / Permit
- 24014-20000-03305
- Plan Check / Job No.
- B24VN10953
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- **ePlan** Addition and Remodel to (E) Single Family Dwelling
- Permit Issued
- Issued on 9/24/2024
- Issuing Office
- Current Status
- CofO Issued on 5/22/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/29/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/31/2024 | EDWIN ESPIN |
| Corrections Issued | 8/1/2024 | EDWIN ESPIN |
| Plan Check Approved | 9/23/2024 | EDWIN ESPIN |
| Issued | 9/24/2024 | APPLICANT |
| CofO in Progress | 5/12/2025 | WILLIAM WREN |
| Permit Finaled | 5/22/2025 | RUBEN SALAS |
| CofO Issued | 5/22/2025 | RUBEN SALAS |
| Permit Finaled | 5/22/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 9/12/2024 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 9/13/2024 | RYAN CASTRO |
| Grading Pre-Inspection | Cleared | 9/16/2024 | CHARLES POWELL |
| Sewer availability | Cleared | 9/20/2024 | RYAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/29/2025 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 1/31/2025 | Approved | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 2/19/2025 | Partial Approval | WILLIAM WREN |
| Insulation | 2/19/2025 | Partial Approval | WILLIAM WREN |
| Wood Frame | 2/19/2025 | Corrections Issued | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 2/21/2025 | Approved | WILLIAM WREN |
| BUILDING-Rough-Frame | 2/28/2025 | Partial Approval | ROBERT GOLD |
| ELECTRICAL-Rough | 2/28/2025 | Approved | ROBERT GOLD |
| HVAC-Rough | 2/28/2025 | Approved | ROBERT GOLD |
| PLUMBING-Rough | 2/28/2025 | Approved | ROBERT GOLD |
| Insulation | 3/6/2025 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 3/6/2025 | Approved | WILLIAM WREN |
| Drywall Nailing | 3/10/2025 | Approved | WILLIAM WREN |
| BUILDING-Rough-Frame | 4/25/2025 | Partial Approval | JACK KARGODORIAN |
| Final | 4/25/2025 | Corrections Issued | JACK KARGODORIAN |
| Green Building Final | 4/25/2025 | Approved | JACK KARGODORIAN |
| Green Building Rough | 4/25/2025 | Approved | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 4/25/2025 | SGSOV Not Ready | JACK KARGODORIAN |
| Smoke Detectors | 4/25/2025 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 4/29/2025 | Approved | WILLIAM WREN |
| Final | 4/29/2025 | Not Ready for Inspection | WILLIAM WREN |
| SGSOV-Seismic Gas S/O Valve | 4/29/2025 | SGSOV Approved | WILLIAM WREN |
| Final | 5/5/2025 | OK to Issue CofO | WILLIAM WREN |