21047 W BALTAR ST 91304
Certificate Information: 21047 W BALTAR ST 91304
- Application / Permit
- 24014-20000-03304
- Plan Check / Job No.
- B24VN10948
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Eplan: Convert (E) breezeway to laundry room and ground floor addition to an (E) 1-Story SFD w/Attached Garage
- Permit Issued
- Issued on 8/26/2024
- Issuing Office
- Current Status
- CofO Issued on 12/3/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/26/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/29/2024 | DAVID CASTILLO |
| Corrections Issued | 7/30/2024 | DAVID CASTILLO |
| Plan Check Approved | 8/23/2024 | DAVID CASTILLO |
| Issued | 8/26/2024 | APPLICANT |
| CofO in Progress | 11/14/2024 | ALEXANDER HANDY |
| Permit Finaled | 12/3/2024 | JOHN JANSON |
| CofO Issued | 12/3/2024 | JOHN JANSON |
| Permit Finaled | 12/3/2024 | JOHN JANSON |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 8/6/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 8/6/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 8/7/2024 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Santos,, Michael; Lic. No.: C77657 | 16202 ORION AVE CHINO, CA 91708 |
Inspector Information
| DAVID FASTIGGI, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/1/2024 | Conditional Approval | ALEXANDER HANDY |
| Footing/Foundation/Slab | 10/1/2024 | Corrections Issued | ALEXANDER HANDY |
| ELECTRICAL-Rough | 10/11/2024 | Approved | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/11/2024 | Approved | ARUTYUN MADATYAN |
| Green Building Rough | 10/11/2024 | No Access for Inspection | ARUTYUN MADATYAN |
| PLUMBING-Rough | 10/11/2024 | Approved | ARUTYUN MADATYAN |
| BUILDING-Rough-Frame | 10/21/2024 | Approved | ARUTYUN MADATYAN |
| Green Building Rough | 10/21/2024 | Approved | ARUTYUN MADATYAN |
| Insulation | 10/21/2024 | Approved | ARUTYUN MADATYAN |
| Interior/Exterior Lathing | 10/21/2024 | Partial Approval | ARUTYUN MADATYAN |
| Drywall Nailing | 10/25/2024 | Approved | ARUTYUN MADATYAN |
| ELECTRICAL-Final | 11/13/2024 | Approved | ALEXANDER HANDY |
| Final | 11/13/2024 | OK to Issue CofO | ALEXANDER HANDY |
| Footing/Foundation/Slab | 11/13/2024 | Approved | ALEXANDER HANDY |
| Green Building Final | 11/13/2024 | Approved | ALEXANDER HANDY |
| HVAC-Final | 11/13/2024 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 11/13/2024 | Approved | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 11/13/2024 | SGSOV Approved | ALEXANDER HANDY |
| Smoke Detectors | 11/13/2024 | Approved | ALEXANDER HANDY |