7013-7013 1/2 W ESTEPA DR 91042

Certificate Information: 7013-7013 1/2 W ESTEPA DR 91042

Application / Permit
24014-20000-03269
Plan Check / Job No.
B24VN10728
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Eplan: Convert (E) Attached Garage to ADU w/Addition per LAMC 12.22 A.33(c) and (d), and convert portion of attached garage to be part of SFD, NFPA 13D-Fire Sprinklers
Permit Issued
Issued on 12/3/2024
Issuing Office
Current Status
CofO Issued on 7/31/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/5/2024 APPLICANT
Assigned to Plan Check Engineer 8/8/2024 DAVID CASTILLO
Corrections Issued 8/8/2024 DAVID CASTILLO
Applicant returned to address corrections 11/26/2024 JOHNPAUL ISIP
Plan Check Approved 12/2/2024 DAVID CASTILLO
Issued 12/3/2024 APPLICANT
CofO in Progress 6/26/2025 DAVID ANDERSON
Permit Finaled 7/31/2025 RUBEN SALAS
CofO Issued 7/31/2025 RUBEN SALAS
Permit Finaled 7/31/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 8/26/2024 EDGAR ALCARAZ
Roof/Waste drainage to street Cleared 8/26/2024 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 8/29/2024 EDGAR ALCARAZ
Sewer availability Cleared 8/29/2024 EDGAR ALCARAZ
Grading Pre-Inspection Cleared 8/30/2024 LANNY MERRICK
Specific Plan Cleared 9/27/2024 JOSHUA ORDONEZ
Construction near power lines Cleared 11/14/2024 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Vartanian,, Albert; Lic. No.: NA39989       ,

Inspector Information

MATTHEW NELSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/31/2025 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 2/3/2025 Corrections Issued DAVID ANDERSON
Footing/Foundation/Slab 2/7/2025 Not Ready for Inspection DAVID ANDERSON
Footing/Foundation/Slab 2/19/2025 Approved DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 2/28/2025 Partial Approval DAVID ANDERSON
Rough-Elec/Plmb/HVAC 3/21/2025 Partial Approval DAVID ANDERSON
Deputy Wood Construction 4/10/2025 Conditional Approval DAVID MATSON
BUILDING-Rough-Frame 4/14/2025 Approved DAVID ANDERSON
Green Building Rough 4/14/2025 Approved DAVID ANDERSON
HVAC-Rough 4/14/2025 Approved DAVID ANDERSON
Verify Sprinkler Sign Off 4/14/2025 Approved DAVID ANDERSON
Insulation 4/18/2025 Approved DAVID ANDERSON
Interior/Exterior Lathing 4/18/2025 Approved DAVID ANDERSON
Rough-Elec/Plmb/HVAC 4/18/2025 Approved DAVID ANDERSON
Drywall Nailing 4/22/2025 Approved MICHAEL CORTEZ
Final 6/18/2025 Corrections Issued DAVID ANDERSON
Green Building Final 6/18/2025 Approved DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 6/18/2025 SGSOV Approved DAVID ANDERSON
Smoke Detectors 6/18/2025 Approved DAVID ANDERSON
Final 6/25/2025 Corrections Issued DAVID ANDERSON
Final 6/25/2025 OK to Issue CofO DAVID ANDERSON
Service/Power Release 6/25/2025 Approved DAVID ANDERSON